Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CM 2113 Wang Test 2 – 50 Exam Questions & Verified Answers (Updated 2026)

Beoordeling
-
Verkocht
-
Pagina's
14
Cijfer
A+
Geüpload op
02-04-2026
Geschreven in
2025/2026

CM 2113 Wang Test 2 – 50 Exam Questions & Verified Answers (Updated 2026)CM 2113 Wang Test 2 – 50 Exam Questions & Verified Answers (Updated 2026)CM 2113 Wang Test 2 – 50 Exam Questions & Verified Answers (Updated 2026)vv

Instelling
CM 2113 Wang
Vak
CM 2113 Wang

Voorbeeld van de inhoud

CM 2113 Wang Test 2 – 50 Exam Questions & Verified
Answers (Updated 2026)


Exam Questions & 100% Verified Revised Answers (Updated)

Course: CM 2113 – Construction Project Management & Controls
Instructor: Professor Wang
Test: 2 (Mid-term coverage: Scheduling, Cost Control, Resource Management, Risk)




Section I – Multiple Choice (30 points)

1. In a Critical Path Method (CPM) network, the activity that has zero total float is called a:
A) Dummy activity
B) Critical activity
C) Slack activity
D) Free-float activity

Answer: B) Critical activity
Revised explanation: Critical activities have zero total float; any delay extends the project
duration.



2. Which of the following is a direct cost in a construction project?
A) Office rent for the home office
B) Project manager’s salary allocated to the job site
C) Depreciation of company-wide equipment
D) Advertising for new projects

Answer: B) Project manager’s salary allocated to the job site
Revised explanation: Direct costs are specifically attributable to a project (labor, materials,
equipment, site supervision). Home office overhead is indirect.



3. If an activity has an Early Start (ES) of day 5, Late Start (LS) of day 8, and duration of 3
days, the Total Float is:
A) 0
B) 3
C) 5
D) 8

Answer: B) 3
*Calculation: Total Float = LS – ES = 8 – 5 = 3 days.*

, 4. In resource leveling, the primary goal is to:
A) Minimize project duration
B) Reduce the critical path
C) Smooth resource demand within available limits
D) Increase the number of activities in parallel

Answer: C) Smooth resource demand within available limits
Revised explanation: Resource leveling shifts non-critical activities to avoid peaks and
valleys, keeping usage within capacity.



5. Which contract type places the greatest risk on the owner?
A) Lump Sum
B) Guaranteed Maximum Price (GMP)
C) Cost Plus Fixed Fee
D) Unit Price

Answer: C) Cost Plus Fixed Fee
Revised explanation: Owner pays all actual costs plus a fee; cost overruns are borne by the
owner.



Section II – Short Answer (40 points)

6. Define the term “Total Float” and explain why it is important for schedule compression.

Answer:
Total Float is the amount of time an activity can be delayed without delaying the project
completion date. It is calculated as LS – ES or LF – EF.
Importance for schedule compression: Activities with float can be delayed or used to shift
resources to critical activities. When compressing (crashing) a schedule, you focus on critical
activities (zero float) first because reducing their duration directly shortens the project.



7. List four typical components of an Earned Value Management (EVM) report and give the
formula for Cost Performance Index (CPI).

Answer:
Components:

• Planned Value (PV)

• Earned Value (EV)

• Actual Cost (AC)

• Budget at Completion (BAC)

CPI formula:

CPI=EVACCPI=ACEV

CPI > 1 indicates under budget; CPI < 1 indicates over budget.

Geschreven voor

Instelling
CM 2113 Wang
Vak
CM 2113 Wang

Documentinformatie

Geüpload op
2 april 2026
Aantal pagina's
14
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$16.39
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
cephasmuriithi Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
79
Lid sinds
2 jaar
Aantal volgers
7
Documenten
715
Laatst verkocht
1 week geleden
STUDENT HELP

96% PASS GUARANTEED . NO RETAKE PASS OR MONEY BACK

3.9

14 beoordelingen

5
9
4
0
3
2
2
1
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen