|Questions|Answers|Explanation
YouMnoticeMthatMaMprojectMusingMtheMpredictiveMapproachMisMbehindMscheduleMforMfo
urMoutMofMtheMfiveMweeks.MYouMperformMaMtrendManalysisMandMpredictMthatMtheMpr
ojectMwillMalsoMbeMbehindMthisMweek.MYouMareMinMtheMprocessMofMsubmittingMaMcha
ngeMrequestMtoMgetMtheMscheduleMbackMonMtrack.MWhatMprocessMgroupMareMyouMin?
a.MInitiating
b.MPlanning
c.MMonitoringMandMControlling
d.MClosingM-MAnswerMc.MMonitoringMandMControlling
Explanation:
Domain:M
I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
01M-MBecomingMaMCertifiedMAssociateMinMProjectMManagementM(CAPM)
JasonMwasMrecentlyMhiredMtoMcreateMaMnewMproduct.MTheMproductMwillMbeMcomplexM
andMwillMrequireMmanyMyearsMtoMcompleteMandMinvolveMmanyMstakeholdersMfromMvari
ousMgroups.MJasonMhasMdecidedMitMwillMbeMbestMtoMbreakMupMtheMproductMintoMsma
llerMsubprojectsMthatMareMmanagedMseparately.MWhatMisMJasonMmanaging?
a.MProgram
b.MPortfolio
c.MProject
d.MOperationsM-MAnswerMa.MProgram
Explanation:
AMprogramMconsistsMofMsimilarlyMgroupedMprojects.
Domain:M
,I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
02M-MProjectsMandMProjectMManagement
WhichMofMtheMfollowingMareMnotMprojectMconstraints?
a.MScope,Mquality,MandMschedule
b.MScope,Mcost,MandMschedule
c.MResource,Mrisk,MandMcost
d.MProcurement,Missues,MandMopportunitiesM-
MAnswerMd.MProcurement,Missues,MandMopportunities
Explanation:
Scope,Mquality,Mschedule,Mbudget/cost,Mresources,MandMrisksMareMsomeMofMtheMmostMi
mportantMprojectMconstraints.
Domain:M
I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
02M-MProjectsMandMProjectMManagement
InMaMproject,Mlaws,Mcompliance,MandMregulatoryMrequirementsMareMconsidered:
a.Massumptions
b.Mconstraints
c.Mnegotiable
d.MirrelevantM-MAnswerMb.Mconstraints
Explanation:
FailingMtoMcomplyMwithMgovernmentMagenciesMandMregulationsMcanMhaveManMimpactMo
nMaMproject,MandMtheMgovernmentMshouldMthereforeMbeMconsideredMstakeholders.MAny
MspecificationsMandMrequirementsMbyMtheMgovernmentMwouldMthereforeMbeMconsidered
Mconstraints.
,Domain:M
I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
02M-MProjectsMandMProjectMManagement
YouMwillMbeMtheMprojectMmanagerMforMaMnewMprojectMinvolvingMaMgloballyMdistributed
MteamMacrossMmanyMcountries.MToMmitigateMconflictMwithMfunctionalMmanagers,MyouMa
skMtheMprojectMsponsorMforMassistance.MWhatMshouldMbeMdone?
a.MCreateMaMprojectMcharterMandMlistMtheMauthorityMandMresponsibilitiesMofMtheMproje
ctMmanager.
b.MMeetMwithMeveryMfunctionalMmanagerMandMinformMthemMyouMhaveMcontrolMofMthe
irMteams.
c.MCreateMaMhumanMresourcesMplan.
d.MMeetMwithMeveryMteamMmemberMandMinformMthemMthatMyouMareMinMcharge.M-
MAnswerMa.MCreateMaMprojectMcharterMandMlistMtheMauthorityMandMresponsibilitiesMof
MtheMprojectMmanager.
Explanation:
BecauseMtheMprojectMmanagerMwillMhaveMtoMcompeteMwithMfunctionalMmanagersMforMt
eamMmembers'Mtime,MtheMprojectMcharterMwouldMbeMtheMbestMplaceMtoMoutlineMhow
MmuchMauthorityMmanagerMhasMoverMtheMproject.
Domain:M
I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
02M-MProjectsMandMProjectMManagement
WhichMofMtheMfollowingMisMnotManMattributeMofMaMproject?
a.MDefinitiveMstartMdate
b.MDefinitiveMendMdate
c.MOngoingMwithMnoMdefinitiveMendMdate
, d.MResultsMinMaMproduct,Mservice,MorMresultM-
MAnswerMc.MOngoingMwithMnoMdefinitiveMendMdate
Explanation:
Projects,MbyMdefinition,MareMtemporary.MAMprojectMhasMdefinitiveMstartMandMendMdates
MandMresultsMinMaMproduct,Mservice,MorMresult.
Domain:M
I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
02M-MProjectsMandMProjectMManagement
YouMhaveMbeenMassignedMtoMaMprojectMtoMopenMaMnewMveterinaryMclinic.MYouMneed
MtoMmeetMwithMtheMidentifiedMstakeholdersMtoMdetermineMtheMbestMwaysMtoMcommu
nicateMwithMthemMandMtoMgetMthemMengaged.MWhatMprocessMgroupMareMyouMin?
a.MInitiating
b.MPlanning
c.MExecuting
d.MMonitoringMandMControllingM-MAnswerMb.MPlanning
Explanation:
YouMareMinMtheMPlanningMprocessMgroupMbecauseMyouMareMmeetingMwithMtheMidentifi
edMstakeholdersMtoMidentifyMhowMtheyMshouldMbeMcommunicatedMwithMandMtoMkeepM
themMengaged.MThisMisMdoneMduringMplanning.
Domain:M
I.MProjectMManagementMFundamentalsMandMCoreMConcepts
Objective:
02M-MProjectsMandMProjectMManagement
AMstakeholderMisMsayingMtheyMareMnotMreceivingMprojectMstatusMreportsMfrequentlyMen
ough.MYouMreviewMtheMcommunicationMmanagementMplanMandMdiscoverMsomeMdiscrepa