7. You are a contracting officer who has a $260,000
commercial contract. You decide you need to terminate
the contract because the contractor has failed to perform.
What is the name of this type of termination?
A. For Noncompliance
B. For Cause
C. For Default
D. For Failure - Answer-B. For Cause
Feedback: See FAR 12.403(a)
8. Simplified Acquisition Procedures (SAP) should:
A. Promote competition to the maximum extent practicable
,2|Page
B. Consider all quotations or offers, regardless of the time
they are received, if they are the most reasonable
C. Promote the use of current vendors for time-saving
purposes
D. Equally consider all businesses, large or small -
Answer-A. Promote competition to the maximum extent
practicable
Feedback: See FAR 13.003(h)
9. In a Determination and Findings, the findings are:
A. A conclusion
B. Support for the determination
C. Not included in the written record
D. Not required - Answer-B. Support for the determination
Feedback: See FAR 1.701
10. Acquisition planning should begin:
,3|Page
A. When a purchase request is received
B. When a statement of work is received
C. As soon as the agency need is identified
D. Within 30 days of receipt of the purchase request -
Answer-C. As soon as the agency need is identified
Feedback: See FAR 7.104(a)
11. When using FAR part 12 procedures, the technical
evaluation would normally include examination of such
things as product literature, product samples (if
requested), technical features, and:
A. Management plans
B. Manufacturing plans
C. Quality assurance plans
D. Warranty provisions - Answer-D. Warranty provisions
Feedback: See FAR 12.602(b)
12. What FAR part covers protests?
, 4|Page
A. FAR part 31
B. FAR part 32
C. FAR part 33
D. FAR part 34 - Answer-C. FAR part 33
Feedback: See FAR 33.000
1. Contractors are responsible for:
A. Appointing Government Contracting Officer
Representatives
B. Managing Government quality control
C. Tendering to the Government for acceptance only those
supplies or services that conform to contract quality
requirements
D. Prescribing Government quality assurance - Answer-C.
Tendering to the Government for acceptance only those
supplies or services that conform to contract quality
requirements