1. A project manager is leading a software development project using a predictive approach. The customer requests a major feature that was not part of the original scope. What should the project manager do first? A. Begin working on the feature immediately to satisfy the customer. B. Submit a change request through the integrated change control process. C. Ask the sponsor for additional budget. D. Add the feature to the risk register. Answer: B Rationale: In a predictive environment, any change to baselined scope must go through integrated change control. The first step is to submit a change request for evaluation. 2. Which process group involves defining a new project or phase by obtaining authorization to start? A. Planning B. Executing C. Initiating D. Monitoring and Controlling Answer: C Rationale: The Initiating process group includes the development of the project charter and formal authorization to begin work. 3. A project team is developing an app using Scrum. Who is responsible for prioritizing the Product Backlog?

Meer zien Lees minder
Instelling
PMP - Project Management Professional
Vak
PMP - Project Management Professional

Voorbeeld van de inhoud

CAPM®ACTUAL EXAM BASED ON THE PMBOK®
GUIDE (7TH EDITION) AND THE CERTIFIED
ASSOCIATE IN PROJECT MANAGEMENT
CURRICULUM


1. A project manager is leading a software development project using a predictive
approach. The customer requests a major feature that was not part of the original scope.
What should the project manager do first?
A. Begin working on the feature immediately to satisfy the customer.
B. Submit a change request through the integrated change control process.
C. Ask the sponsor for additional budget.
D. Add the feature to the risk register.

Answer: B
Rationale: In a predictive environment, any change to baselined scope must go through
integrated change control. The first step is to submit a change request for evaluation.




2. Which process group involves defining a new project or phase by obtaining
authorization to start?
A. Planning
B. Executing
C. Initiating
D. Monitoring and Controlling

Answer: C
Rationale: The Initiating process group includes the development of the project charter and
formal authorization to begin work.

,3. A project team is developing an app using Scrum. Who is responsible for prioritizing
the Product Backlog?
A. Scrum Master
B. Development Team
C. Product Owner
D. Project Manager

Answer: C
Rationale: In Scrum, the Product Owner owns and prioritizes the Product Backlog to
maximize value.




4. Which of the following best describes a stakeholder?
A. Anyone who provides funding for the project
B. Any individual or group that can affect or be affected by the project
C. Only the project sponsor and project manager
D. Only customers and end users

Answer: B
Rationale: Stakeholders include all individuals or groups who have an interest in or can
influence the project, positively or negatively.




5. A risk response strategy that involves shifting the impact of a threat to a third party is
called:
A. Mitigate
B. Accept
C. Transfer
D. Enhance

Answer: C
Rationale: Transfer involves shifting risk ownership to a third party, such as through
insurance or warranties.

,6. Which document formally authorizes the project and gives the project manager
authority to apply resources?
A. Project management plan
B. Business case
C. Project charter
D. Stakeholder register

Answer: C
Rationale: The project charter is issued by the sponsor or initiator to formally authorize the
project and assign the project manager.




7. What is the primary purpose of the Work Breakdown Structure (WBS)?
A. To list project risks
B. To sequence project activities
C. To decompose project deliverables into smaller, manageable components
D. To assign resources to tasks

Answer: C
Rationale: The WBS breaks down the total scope of work into manageable pieces called
work packages.




8. Which type of dependency is legally or contractually required?
A. Discretionary
B. External
C. Mandatory
D. Internal

Answer: C
Rationale: Mandatory dependencies are inherent in the nature of the work or required by
law or contract.

, 9. During which process do project team members perform the planned work to meet
project objectives?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing

Answer: B
Rationale: The Executing process group involves completing the work defined in the project
management plan.




10. What is the formula for Cost Variance (CV)?
A. EV – AC
B. EV – PV
C. AC – EV
D. PV – AC

Answer: A
Rationale: CV = Earned Value (EV) – Actual Cost (AC). Positive indicates cost underrun.




11. Which tool is used to identify cause-and-effect relationships in quality
management?
A. Pareto chart
B. Ishikawa (fishbone) diagram
C. Control chart
D. Histogram

Answer: B
Rationale: The fishbone diagram helps identify root causes of a problem by breaking down
potential causes into categories.

Geschreven voor

Instelling
PMP - Project Management Professional
Vak
PMP - Project Management Professional

Documentinformatie

Geüpload op
4 april 2026
Aantal pagina's
33
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$40.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
muriithi Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
11
Lid sinds
2 jaar
Aantal volgers
2
Documenten
1142
Laatst verkocht
2 weken geleden
HERE YOU WILL FIND IT!!!

Think,Explore,Discover and meet a new difference....here I simply want to make what you want.... And Thank You Again For Chosing Me

5.0

1 beoordelingen

5
1
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen