Understand when the final inspection occurs (what other activities should be complete) -
CORRECT ANSWER •At the end of a job Final Inspections are required to close out
the permit and obtain a certificate of occupancy (CO).
In order for the final inspection to be complete these final inspections must also be inspected
•Final Electrical Complete
•Final Plumbing
•Test & Balance Reports
•Special Inspections Report
•Final Fire Complete
Electrical - Know the main components of the final - CORRECT ANSWER •Check
panelboards for connections, wire sizing, grounding.
•Test circuits for power, continuity, grounds.
•AFCI / GFCI circuit breakers or receptacles where required
•All emergency lighting in place
•Exit devices in place.
•Ceiling dropped
•Clearances at panel locations
Plumbing - Main Components - CORRECT ANSWER •Water service and storm
drainage system has been inspected and signed off.
•DWV System tested / Signed off
•Access doors in place for all shut off / isolation valve locations
•Cleanouts
•Backflow prevention as required - sprinkler system, fire protection system - TESTED - 3rd
party
•Vents extending 6" above roof