Manufacturer's field reports
Documentation of the testing and verification actions taken by manufacturer's
representative at the job site, or on sample taken from the job site, on a
portion of the work, during or after installation to confirm compliance with
standards and instructions.
Must be signed by an authorized official of testing laboratory or agency and
state the test results to indicate pass or failure
Closeout Submittals
Documentation to record compliance with technical or administrative
requirements or to establish an administrative mechanism
Special requirements to end a contract or major phase if a multi phase contract
GPV
Guiding principle validation
TPC
Third party certification
, Approving Authority
Office or designated person authorized to approve submittal
Work
On and off site construction required by contract documents, including labor
necessary to produce submittals, construction, materials, products,
equipment, and systems
incorporated or to be incorporated
Submittals
are NOT contract documents. Prepared by subcontractors and material
suppliers, sent to GC to review and approve them, which means the GC has
varified field measurements,
materials have been checked and construction criteria has been coordinated.
Then- the submittals are sent to Designer (if the submittals are NOT checked and
signed by GC,
designer should immediately return them without review). Designer reviews
submittals ONLY for limited purpose of checking for conformance with info
given and correct design intent (designer is NOT responsible for accuracy of
measurements, completeness of details, verifying quantities, or checking
fabrication or installation procedures). If
necessary, the submittals are forwarded (by designer) onto appropriate
consultants for review. Once consultant reviews, they send it back to designer,
who then sends back to GC. Designer may indicate on dwgs that no exceptions
are taken, that marked corrections should be made, that they should be revised
and resubmitted or that they are rejected.
FIO
For information only