Which two plans in the SWPPP must be approved? -
Answer-SWM plan, ESC plan
Does the SWM plan address runoff during or after
construction? - Answer-post-construction
What is the lower limit of the range of imperviousness that
can result in stream degradation? - Answer-10%
What do land disturbing activities consist of? - Answer-
excavating, clearing, grading
LDA threshold for the SWM Act and Regulation - Answer-1
acre or 2500 square feet for Chesapeake Bay
Preservation Act
In situations where an initial exemption was applicable
because LDAs were related to emergency work, VSMP
,2|Page
authority shall be advised of the disturbance within -
Answer-7 days of commencing the LDA and shall submit a
permit application within 30 days of starting the land-
disturbing activity
Localities with MS4 - Answer-must adopt and administer a
stormwater program
Localities without MS4 - Answer-may choose to administer
a VSMP or have DEQ administer the program
DEQ is responsible for enforcing the ____ while locality
____ are responsible for enforcing local ordinances -
Answer-Construction GP, VSMP
A locality VSMP authority must include enforcement
authority and a schedule of civil penalties for enforcement
actions in its local ordinance. The maximum penalty the
authority may issue is - Answer-$32,500 per violation per
day
, 3|Page
Any civil penalty assessed by a court as a result of a
summons issued by a locality VSMP authority must be
paid - Answer-into the locality's treasury
Any person who violates..... shall be subject to a civil
penalty not to exceed - Answer-$32, 500
Chesapeake Bay Preservation Areas that result in a land
disturbance greater than or equal to ____ and less than
____ - Answer-2,500 ft^2, 1 acre
CBPA LDAs must have - Answer-approved E&SC plan,
approved SWM plan, local approval to start land
disturbance, long-term maintenance agreement,
construction record drawings
CBPA LDAs do not require - Answer-Construction GP,
Pollution prevention Plan, Additional control measures to
address TMDL
State entities and linear projects ___ submit a single set of
standards and specifications to DEQ for approval, federal
entities ____ - Answer-must, may