EM 385 (40 HOUR) EXAM QUESTIONS
AND ANSWERS 2026 VERIFIED.
1) For complex or high hazard projects, the SSHO shall have a minimum of ten (10) years of
safety-related work with at least five (5) years experience on similar type projects. -
ANS TRUE
2) All Safety and Health training will be documented in writing, to include the date, name,
content, and ________. - ANS Trainer
The APP plan is an important safety and health policy and program document. Which areas are
addressed within an APP? - ANS a) Signature Sheet
b) Training
c) Statement of Safety and Health Policy
d) all of the above.
The SSHO(s), as a minimum, must have completed ___________ or equivalent - ANS 30 hour
OSHA construction training class
For limited scope supply, service and R&D contracts, the Contracting Officer - ANS may
authorize an abbreviated APP.
Drinking water must be provided at all Continental United States (CONUS) fixed facilities. -
ANS TRUE
@2026/2027 ALLRIGHTS RESERVED.
,Open containers such as barrels, pails, or tanks, may be used for drinking water if properly
sterilized. - ANS FALSE
Toilet facilities should contain the following: - ANS - Separate facilities for males and females
- Hot and cold running water, or tepid running water
- Functioning hand soap (or the equivalent)
Outlets dispensing non-potable water shall: - ANS have a conspicuously posted Caution sign.
Cafeterias or mess halls are not required to comply with state and local regulations. -
ANS FALSE
The best type of ANSI Z308.1 first aid container for a mobile, indoor, or outdoor setting, where
the potential for damage of kit supplies due to environmental factors is not probable, is -
ANS Type III
Medical facilities and personnel expected to treat injured employees shall ______. - ANS - be
informed of the nature of the work to be performed.
- be informed of the injuries/illnesses prevalent to the job site
Employees working outside of their normal geographic area must be informed of any parasitic,
viral and environmental disease endemics after work has begun. - ANS FALSE
When a medical facility or physician is not accessible within five minutes of an injury to a group
of two or more employees for the treatment of injuries, at least two employees on each shift
shall be qualified to administer _______. - ANS First aid and CPR
For projects with more than 300 people, a licensed physician and infirmary should be
established. - ANS TRUE
@2026/2027 ALLRIGHTS RESERVED.
, Vehicle speed shall be limited on curves so that vehicles can be stopped within one-half the
visible distance of the roadway. - ANS TRUE
Signs warning of the presence of construction hazards and requiring unauthorized person to
keep out shall be posted at every ________ feet of fencing. - ANS 150
The design and construction of temporary structures must consider the following loadings -
ANS Seismic forces
Trailers and other temporary structures used as field offices must be: - ANS Anchored to
ground anchors.
Designed to withstand winds.
Meet applicable state or local standards.
* All of the above.
Depending upon the nature and location of the project site, the GDA may determine that
temporary project fencing is not required. - ANS TRUE
Which of the following is not a requirement for using Automatic-Inflatable Personal Flotation
Devices? - ANS type V or better, USCG approved for Commercial Use.
Personal Protective Equipment is a control measure that is used only after a hazard evaluation
identifies hazards associated with a particular job. - ANS TRUE
Certain activities and areas may be considered as non-hard hat areas if: - ANS identified and
properly documented in the AHA.
When employees provide their own safety equipment or PPE, _________ is responsible for
assuring its adequacy in protecting against the hazard and its state of repair. - ANS employer
@2026/2027 ALLRIGHTS RESERVED.
AND ANSWERS 2026 VERIFIED.
1) For complex or high hazard projects, the SSHO shall have a minimum of ten (10) years of
safety-related work with at least five (5) years experience on similar type projects. -
ANS TRUE
2) All Safety and Health training will be documented in writing, to include the date, name,
content, and ________. - ANS Trainer
The APP plan is an important safety and health policy and program document. Which areas are
addressed within an APP? - ANS a) Signature Sheet
b) Training
c) Statement of Safety and Health Policy
d) all of the above.
The SSHO(s), as a minimum, must have completed ___________ or equivalent - ANS 30 hour
OSHA construction training class
For limited scope supply, service and R&D contracts, the Contracting Officer - ANS may
authorize an abbreviated APP.
Drinking water must be provided at all Continental United States (CONUS) fixed facilities. -
ANS TRUE
@2026/2027 ALLRIGHTS RESERVED.
,Open containers such as barrels, pails, or tanks, may be used for drinking water if properly
sterilized. - ANS FALSE
Toilet facilities should contain the following: - ANS - Separate facilities for males and females
- Hot and cold running water, or tepid running water
- Functioning hand soap (or the equivalent)
Outlets dispensing non-potable water shall: - ANS have a conspicuously posted Caution sign.
Cafeterias or mess halls are not required to comply with state and local regulations. -
ANS FALSE
The best type of ANSI Z308.1 first aid container for a mobile, indoor, or outdoor setting, where
the potential for damage of kit supplies due to environmental factors is not probable, is -
ANS Type III
Medical facilities and personnel expected to treat injured employees shall ______. - ANS - be
informed of the nature of the work to be performed.
- be informed of the injuries/illnesses prevalent to the job site
Employees working outside of their normal geographic area must be informed of any parasitic,
viral and environmental disease endemics after work has begun. - ANS FALSE
When a medical facility or physician is not accessible within five minutes of an injury to a group
of two or more employees for the treatment of injuries, at least two employees on each shift
shall be qualified to administer _______. - ANS First aid and CPR
For projects with more than 300 people, a licensed physician and infirmary should be
established. - ANS TRUE
@2026/2027 ALLRIGHTS RESERVED.
, Vehicle speed shall be limited on curves so that vehicles can be stopped within one-half the
visible distance of the roadway. - ANS TRUE
Signs warning of the presence of construction hazards and requiring unauthorized person to
keep out shall be posted at every ________ feet of fencing. - ANS 150
The design and construction of temporary structures must consider the following loadings -
ANS Seismic forces
Trailers and other temporary structures used as field offices must be: - ANS Anchored to
ground anchors.
Designed to withstand winds.
Meet applicable state or local standards.
* All of the above.
Depending upon the nature and location of the project site, the GDA may determine that
temporary project fencing is not required. - ANS TRUE
Which of the following is not a requirement for using Automatic-Inflatable Personal Flotation
Devices? - ANS type V or better, USCG approved for Commercial Use.
Personal Protective Equipment is a control measure that is used only after a hazard evaluation
identifies hazards associated with a particular job. - ANS TRUE
Certain activities and areas may be considered as non-hard hat areas if: - ANS identified and
properly documented in the AHA.
When employees provide their own safety equipment or PPE, _________ is responsible for
assuring its adequacy in protecting against the hazard and its state of repair. - ANS employer