(Verified Answers) 2026
What is included in the contract? - correct answer
referenced as part of the contract.
✅Anything that is
Scope - correct answer
the contract is about?
✅Which core contract element addresses what
When was the contract agreed? - correct answer ✅ Which of the
following is NOT one of the four core elements of a contract?
1,3,4 - correct answer✅ Which of the following may be incorporated
into the contract? 1.) bid documents 3.) Letters, change orders and
specifications. 4.) SOWs, SLAs, RFP, procedures and prices
✅
The bid, negotiation and implementation teams - correct answer
Who should be involved in the formal contract hand over meeting?
Keep Satisfied - correct answer✅ A stakeholder group with a low level
os impact and a high level of dependence on an outcome is represented
as which group type for communication purposes?
Stay informed and maintain confidence - correct answer ✅ By
understanding projects on a stakeholders radar screen, you will
,CCMP Test Questions review Q&As
(Verified Answers) 2026
Build awareness - correct answer ✅ If you are unlikely to be impacted
by a contract and you have little importance towards it then you are
most likely to be categorized as which type of stakeholder?
Both 1 and 2 - correct answer ✅ What should be considered when
identifying a stakeholders important issues? 1.) What programs they
have in the near future. 2.) What they consider to be a risk.
evaluation. This is called a..? - correct answer ✅
A very complex project may require a more segmented approach to
Two cycle evaluation
What are intangible evaluation criteria? - correct answer
that rely on organizational culture and behavior
✅ Factors
When embarking on a long term project, which of the following is often
correct answer ✅
not given adequate consideration at the proposal evaluation stage? -
The suppliers cultural compatibility with the buyer
an RFP - correct answer ✅
When is the earliest you can begin to define the evaluation matrix for
Prior to drafting the RFP
What is the name of the bid evaluation approach that requires a
correct answer ✅
supplier to achieve a satisfactory level on specific evaluation criteria? -
Hurdle
, CCMP Test Questions review Q&As
(Verified Answers) 2026
contracts to be in writing? - correct answer✅
Above what value does the uniform commercial code in the USA require
US $500
procedures? - correct answer
beginning of negotiations.
✅
Of the following, which is the best time to address dispute resolution
Procedures should be agreed at the
What do cross-border contracts involving countries who have signed up
(CISG) provide? - correct answer
specifically excluded.
✅
to the UN convention on contracts for the international sale of goods
CISG automatically applies unless
What effect does the UN convention on contracts for the international
be accepted? - correct answer ✅
sale of goods (CISG) have on stating a time limit in which the offer must
Creates an irrevocable offer
Which of the following statements about offer termination is
true/false? 1.) Offers may not be terminated once they have been
which the offer was made. - correct answer ✅
made, and 2.) Offers may only be terminated using the same method by
Only 2 is true.
Of the following, which timing for the preparation and signing of a NDA
answer ✅
will best protect both customer and suppliers interests? - correct
When RFI documents are issued