FCCM newest Exam with precise detailed answers || || || || || ||
FCCM - ✔✔Florida Certified Contract Manager, 287. 601a
|| || || || || || ||
How many stages in Public Procurement? - ✔✔7
|| || || || || || ||
1st Stage - ✔✔Identification Stage:
|| || || || ||
* Need id
|| ||
* budget id
|| ||
* purchasing strategy
|| ||
Objective for (Need ID Stage) - ✔✔Identify the categories of purchases available to use
|| || || || || || || || || || || || || ||
when contracting for commodities or contractual services.
|| || || || || ||
What would be an procurement purchase that cannot be delayed? - ✔✔Emergency
|| || || || || || || || || || || ||
Purchases (Non-Competitive) ||
Exceptional Purchases (Non-Competitive) - ✔✔* Respect || || || || ||
* Pride
||
* State Term Contract (STC)
|| || || ||
* Alternative Contract Source (ACS)
|| || || ||
*Single Source || ||
* Exempt Commodities and Contractual Services,
|| || || || ||
Rule 60A-1.002(4)
||
, 2
Competitive Solicitation - ✔✔The total cost of the commodities or contractual services
|| || || || || || || || || || || ||
exceed services exceeds 35,000 (Category 2)
|| || || || ||
What is stage 2 process called? - ✔✔Pre-Solicitation Process:
|| || || || || || || || ||
Develop background information needed for a successful competitive solicitation and which
|| || || || || || || || || ||
method is appropriate.
|| || ||
Stage 2: Payment Methods - ✔✔* Cost Reimbursement
|| || || || || || ||
* Fixed Price
|| ||
* Fixed Rate
|| || ||
*Combination
Cost Reimbursement - ✔✔The provider submits a request for reimbursement and is
|| || || || || || || || || || || ||
reimbursed for allowable cost incurred that are directly related to the commodities or
|| || || || || || || || || || || || ||
services in the contract/grant. || || ||
Fixed price - ✔✔Project is divided into intervals and payment is distributed at those
|| || || || || || || || || || || || || ||
intervals.
*Bi-weekly
* Monthly
||
* Quarterly
||
Fixed rate - ✔✔Payments are based on a fixed rate.
|| || || || || || || || ||
*Hourly rate of pay || || ||
*Per unit delivered
|| ||