FCCM Exam questions with accurate detailed solutions
|| || || || || ||
Days to file a written protest - ✔✔10 days
|| || || || || || || ||
Approval and Inspection of goods/services duration - ✔✔5 days
|| || || || || || || ||
Invoice submission deadline to CFO - ✔✔20 days
|| || || || || || ||
Time before a person can work for an entity with a contract with their former agency - ✔✔2
|| || || || || || || || || || || || || || || || ||
years
||
Years a contract manager may not oversee a vendor they were employed by - ✔✔5 years
|| || || || || || || || || || || || || || ||
Deadline for invoices to reach the CFO - ✔✔20 days
|| || || || || || || || ||
Formal written protest filing period - ✔✔10 days (72 hours to provide notice)
|| || || || || || || || || || || ||
Methods for vendor questions - ✔✔Written Q&A period and Pre-response conference
|| || || || || || || || || ||
Required Reviews for Category 3 ($65,000) - ✔✔Programmatic Review, Legal Review,
|| || || || || || || || || || ||
Financial Review ||
Solicitation requirement if need is above $35,000 - ✔✔Competitive
|| || || || || || || ||
Payment distribution method - ✔✔Fixed Price
|| || || || ||
, 2
Document used in competitive solicitation - ✔✔Scope of Work
|| || || || || || || ||
Legally required analysis for non-competitive awards - ✔✔Cost Analysis
|| || || || || || || ||
Elements accepted when closing out a contract - ✔✔Deliverables, Final Payment, Final
|| || || || || || || || || || || ||
Invoice
Required elements of a contract - ✔✔Scope of Work, Deliverables, Financial Consequences
|| || || || || || || || || || ||
Liaison responsibility according to 287.057 F.S. - ✔✔Contract Manager
|| || || || || || || ||
Contract type for hourly work payment - ✔✔Fixed Rate
|| || || || || || || ||
Provider onboarding requirement regarding Scope of Work - ✔✔Never
|| || || || || || || ||
Florida Statute notice requirement for public meetings - ✔✔7 days prior to meeting
|| || || || || || || || || || || ||
Focus of Request for Proposal (RFP) - ✔✔Price & Quality
|| || || || || || || || ||
Examples of NOT excusable delays - ✔✔Financial Problems, Lack of Equipment, Personal
|| || || || || || || || || || || ||
Issues, Lack of materials, Lack of Knowledge
|| || || || || ||
Contact for vendor inquiries - ✔✔Procurement Officer
|| || || || || ||
Types of Termination - ✔✔Convenience and Cause
|| || || || || ||