TN BC Contractors exam with accurate detailed solutions
|| || || || || || ||
After installation and adequate fastening, floor decks serve several purposes:
|| || || || || || || || ||
A. Acts as a working platform
|| || || || ||
B. Stabilizes the frame
|| || ||
C. Serves as concrete form for the slab
|| || || || || || ||
D. All the above - ✔✔Steel Deck pg 6:
|| || || || || || || || ||
D. All the above
|| || ||
Composite floor deck is normally installed so the __________________ - ✔✔Steel Deck pg
|| || || || || || || || || || || || ||
6:
||
Panel ends do not overlap || || || ||
Roof deck is not designed to act compositely with other materials. The roof
|| || || || || || || || || || || || ||
deck________________________ - ✔✔Steel Deck pg 7: || || || || ||
Acts alone in transferring horizontal and vertical loads into the building frame.
|| || || || || || || || || || ||
Roof deck is typically installed to end lap approximately _________ inches over supports. -
|| || || || || || || || || || || || || ||
✔✔Steel Deck pg 7: || || ||
2"
___________________ can be used in the same manner as floor deck. Electrical, telephone || || || || || || || || || || || || ||
and computer wires are easily run through the chase created between the deck panel and
|| || || || || || || || || || || || || || ||
the bottom sheet. - ✔✔Steel Deck pg 8:
|| || || || || || ||
Cellular Deck ||
,2
A 3' x 12" composite floor deck will have a nominal thickness range of. 03 inches to. 06
|| || || || || || || || || || || || || || || || || ||
inches and a weight range of ____ to _____ psf - ✔✔Steel Deck pg 9:
|| || || || || || || || || || || || || ||
2 to 4 psf
|| || ||
F deck may also be referred to as______________ for the name,. 03 inches two. 06 inches
|| || || || || || || || || || || || || || || ||
for the thickness and 2 to 4 PSF for the weight. - ✔✔Steel Deck pg 10:
|| || || || || || || || || || || || || || ||
1 1/2" X 6" Intermediate Rib
|| || || || ||
The weight range for cellular floor decking is__________ - ✔✔Steel Deck pg 12:
|| || || || || || || || || || || ||
4 to 7 PSF
|| || ||
A heavy duty form decks name used in centering is______ Form deck with a thickness
|| || || || || || || || || || || || || || ||
of_____ to _____ And a weight range of one to two PSF - ✔✔Steel Deck pg 11:
|| || || || || || || || || || || || || || || ||
15/16" and 0.017" to 0.040" || || || ||
Steel deck is banded into bundles that can weigh several thousand pounds but the deck
|| || || || || || || || || || || || || || ||
bundle weight will be limited to a maximum of_______________ For deck to be applied to
|| || || || || || || || || || || || || || ||
joists. - ✔✔Steel Deck pg 14: || || || || ||
4000 lbs ||
If ground storage is needed, the deck bundles should be______________ - ✔✔Steel Deck pg
|| || || || || || || || || || || || ||
18:
||
Stored off the ground, with one end elevated to provide drainage.
|| || || || || || || || || ||
Deck bundles must________ be placed on the frame near a main supporting beam at a
|| || || || || || || || || || || || || || ||
column or a wall - ✔✔Steel Deck pg 18: || || || || || || || ||
ALWAYS
,2
Bundles should be landed so that the ___________________________ rather than having
|| || || || || || || || || || ||
one or both ends cantilevered. - ✔✔Steel Deck pg 22:
|| || || || || || || || ||
Ends of the bundles rest on a bearing surface
|| || || || || || || ||
Are you working area should be at least _________ feet wide. - ✔✔Steel Deck pg 24:
|| || || || || || || || || || || || || || ||
12
When aligning the edge (side) lap, the worker should__________ - ✔✔Steel Deck pg 25:
|| || || || || || || || || || || || ||
Kneel
Deck fastening to the structural frame can be accomplished with: - ✔✔Steel Deck pg 28:
|| || || || || || || || || || || || || ||
Welds, self drilling screws, air driven, and power driven
|| || || || || || || ||
Screws are typically_____ or ________ With a special drill point when used to attach
|| || || || || || || || || || || || || ||
decking. - ✔✔Steel Deck pg 30: || || || || ||
#12s or 1/4" in diameter
|| || || ||
Weld washers are not recommended for deck thickness of_____ (Minimum of 22 gauge)
|| || || || || || || || || || || || ||
and greater - ✔✔Steel Deck pg 32:
|| || || || || ||
0.028"
A good weld will have______ Or more of its perimeter working. - ✔✔Steel Deck pg 34:
|| || || || || || || || || || || || || || ||
75% (7/8ths previously)
|| ||
Welding side laps is not recommended for decks type____ Or lighter (0.028" min.) -
|| || || || || || || || || || || || || ||
✔✔Steel deck pg 34: || || ||
22
, 2
Weld washers should___________ Be used at side laps between supports - ✔✔Steel deck pg
|| || || || || || || || || || || || || ||
34:
Never
No reinforcing is generally required for an opening of 6 inches as long as not more
|| || || || || || || || || || || || || || || ||
than____ webs are removed - ✔✔Steel Deck pg 37: || || || || || || || ||
2
For holes or dents greater than a rib (8 inches to 13 inches), It is advisable to use
|| || || || || || || || || || || || || || || || || ||
a____________ to cover it - ✔✔Steel Deck pg 38: || || || || || || || ||
0.057" minimum plate || ||
The deck should have been selected to provide at least___________ pounds per square foot
|| || || || || || || || || || || || || ||
capacity as a working platform. - ✔✔Steel Deck pg 43:
|| || || || || || || || ||
50
If the deck is to act as a diaphragm during construction, it must be realize that the
|| || || || || || || || || || || || || || || || ||
diaphragm is not effective until all deck units are_______________ - ✔✔Steel Deck pg 43:
|| || || || || || || || || || || || ||
Placed and fully connected || || ||
A chimney shall extend at least how many feet higher than any portion of a building within
|| || || || || || || || || || || || || || || || ||
10 feet? ||
A. 2' ||
B. 3' ||
C. 5' ||
D. 6' - ✔✔IBC pg 444
|| || || || ||