Unrestricted CSL Practice Questions with accurate detailed solutions || || || || || || ||
Who is authorized to enforce the provisions of 780 CMR, review/issue permit applications,
|| || || || || || || || || || || || ||
issue noticed/orders, and make required inspections? - ✔✔Building official
|| || || || || || || ||
IRC Amendments R104.1 General
|| || ||
Who shall receive and issue permits? - ✔✔Building official
|| || || || || || || ||
IRC Amendments R104.2 Application and Permits
|| || || || ||
Who shall issue notices and orders? - ✔✔Building official
|| || || || || || || ||
IRC Amendments R104.3
|| ||
who shall make the required inspections? - ✔✔Building official
|| || || || || || || ||
IRC Amendments R104.4
|| ||
A permit is required for work including but not limited to repairs for substantial cutting of
|| || || || || || || || || || || || || || || ||
walls - ✔✔IRC Amendments R105.2.2 Repairs
|| || || || ||
The building official shall issue or deny a permit within ___ days of filing - ✔✔30 days
|| || || || || || || || || || || || || || || ||
IRC Amendments R105.3.1 Action on Application
|| || || || ||
How many days does a building inspector have to act on a permit application
|| || || || || || || || || || || || ||
a.) 180 days
|| ||
b.) 90 days
|| ||
c.) 30 days
|| ||
d.) 60 days - ✔✔c.) 30 days
|| || || || || ||
, 2
IRC Amendments R105.3.1 Action on Application
|| || || || ||
Every permit issued shall become invalid unless the work authorized by such permit is
|| || || || || || || || || || || || || ||
commended within ___ days. The building official can grant one or more extensions for
|| || || || || || || || || || || || || ||
periods not more than ____ days - ✔✔180 days, 90 days
|| || || || || || || || || ||
IRC Amendments R105.3.2 Time Limitation on Application
|| || || || || ||
A permit may be suspended or revoked for all of the following reasons, except
|| || || || || || || || || || || || ||
a.) where it is issued in error
|| || || || || ||
b.) on the basis of incomplete information
|| || || || || ||
c.) where issued in violation of jurisdictional ordinance
|| || || || || || ||
d.) where other permits by the contractor have been voided - ✔✔d.) where other permits by
|| || || || || || || || || || || || || || || ||
the contractor have been voided
|| || || ||
IRC Amendments R105.6
|| ||
Submittal documents consisting of construction documents, and other data shall be
|| || || || || || || || || || ||
submitted in ____ or more sets with each application for a permit - ✔✔two sets
|| || || || || || || || || || || || || ||
IRC Amendments R107.1 Submittal Documents
|| || || ||
Townhouse buildings greater than 35,000 square feet require a ______ - ✔✔registered
|| || || || || || || || || || || ||
design professional ||
IRC Amendments R107.1.6 Townhouse buildings greater than 35,000 square feet
|| || || || || || || || ||
On which drawing will you find the building location and lot lines? - ✔✔Site plan/plot plan
|| || || || || || || || || || || || || || ||
IRC Amendments R107.2 Site Plan or Plot Plan
|| || || || || || ||