Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CAPM (Certified Associate in Project Management) COMPLETE EXAM QUESTIONS AND 100% VERIED ANSWERS WITH LATEST VERSION 2026.

Beoordeling
-
Verkocht
-
Pagina's
31
Cijfer
A+
Geüpload op
12-04-2026
Geschreven in
2025/2026

CAPM (Certified Associate in Project Management) COMPLETE EXAM QUESTIONS AND 100% VERIED ANSWERS WITH LATEST VERSION 2026.

Instelling
CAPM
Vak
CAPM

Voorbeeld van de inhoud

CAPM (Certified Associate in Project Management)
COMPLETE EXAM QUESTIONS AND 100% VERIED
ANSWERS WITH LATEST VERSION 2026.


1. What is the primary purpose of a project charter?
A. To define detailed project tasks
B. To formally authorize the project
C. To assign project team members
D. To create the project schedule
Correct Answer: B
Rationale: The project charter formally authorizes the project and gives the project
manager authority to apply resources. Other options relate to planning activities, not
authorization.



2. Which process group includes defining the scope and developing the schedule?
A. Initiating
B. Planning
C. Executing
D. Monitoring and Controlling
Correct Answer: B
Rationale: Planning involves defining scope, schedule, cost, and other baselines.
Initiating authorizes the project, while executing and monitoring focus on
implementation and control.



3. What is a key output of the Define Scope process?
A. Project Charter
B. Scope Statement
C. Risk Register
D. Stakeholder Register
Correct Answer: B
Rationale: The scope statement details project and product scope. The charter comes
earlier, while risk and stakeholder registers belong to other processes.



4. Which tool is used to break down project deliverables into smaller components?
A. Gantt Chart
B. Work Breakdown Structure (WBS)
C. Pareto Chart
D. Fishbone Diagram
Correct Answer: B
Rationale: The WBS decomposes deliverables into manageable work packages. Other
tools serve different purposes such as scheduling or quality analysis.

,5. A project manager identifies stakeholders and documents their interests. This occurs
in which process?
A. Identify Stakeholders
B. Plan Communications
C. Manage Stakeholder Engagement
D. Monitor Risks
Correct Answer: A
Rationale: Identifying stakeholders and documenting their interests is done in the
Identify Stakeholders process. Other processes involve planning or managing
engagement.



6. What is the main purpose of a risk register?
A. To document project costs
B. To list identified risks and responses
C. To define project scope
D. To track stakeholder communication
Correct Answer: B
Rationale: The risk register contains identified risks, their analysis, and response
strategies. It is central to risk management.



7. Which type of organization gives the project manager the most authority?
A. Functional
B. Weak Matrix
C. Balanced Matrix
D. Projectized
Correct Answer: D
Rationale: In a projectized organization, the project manager has the highest level of
authority. Functional and matrix structures limit this authority.



8. What does the critical path represent?
A. The shortest path in a project
B. The path with the most resources
C. The longest duration path through the project
D. The least expensive path
Correct Answer: C
Rationale: The critical path is the longest path determining the project duration. Any
delay on this path delays the entire project.



9. Which estimate technique uses historical data from similar projects?
A. Parametric Estimating

, B. Analogous Estimating
C. Bottom-Up Estimating
D. Three-Point Estimating
Correct Answer: B
Rationale: Analogous estimating uses historical data from similar projects. Other
techniques use different approaches such as statistical or detailed estimation.



10. What is the main goal of quality assurance?
A. Inspecting deliverables
B. Preventing defects
C. Identifying errors
D. Testing outputs
Correct Answer: B
Rationale: Quality assurance focuses on process improvement to prevent defects,
while quality control focuses on inspection and testing.



11. Which document defines how the project will be executed, monitored, and controlled?
A. Project Charter
B. Project Management Plan
C. Scope Statement
D. Risk Register
Correct Answer: B
Rationale: The project management plan integrates all subsidiary plans and guides
execution and control.



12. What is float (slack) in scheduling?
A. The cost variance
B. The amount of time a task can be delayed without affecting the project
C. The total project duration
D. The number of resources available
Correct Answer: B
Rationale: Float is the amount of time an activity can be delayed without delaying the
project end date.



13. Which communication method is most efficient for large audiences?
A. Interactive
B. Push
C. Pull
D. Verbal
Correct Answer: C
Rationale: Pull communication (e.g., websites, repositories) is best for large
audiences to access information at their convenience.

, 14. What is the main output of the Collect Requirements process?
A. Scope Baseline
B. Requirements Documentation
C. Project Charter
D. Risk Register
Correct Answer: B
Rationale: Requirements documentation captures stakeholder needs and expectations.



15. What does CPI stand for in Earned Value Management?
A. Cost Performance Index
B. Cost Planning Indicator
C. Control Performance Index
D. Cost Project Indicator
Correct Answer: A
Rationale: CPI measures cost efficiency (EV/AC). Other options are incorrect
expansions.



16. If CPI is less than 1, what does it indicate?
A. Under budget
B. On budget
C. Over budget
D. Ahead of schedule
Correct Answer: C
Rationale: CPI < 1 indicates cost inefficiency, meaning the project is over budget.



17. Which risk response strategy involves transferring the impact to a third party?
A. Avoid
B. Mitigate
C. Transfer
D. Accept
Correct Answer: C
Rationale: Transfer shifts risk to a third party, such as through insurance or
contracts.



18. What is the main purpose of the Perform Integrated Change Control process?
A. Approve scope changes only
B. Review and manage all change requests
C. Update risk register
D. Manage stakeholders
Correct Answer: B

Geschreven voor

Instelling
CAPM
Vak
CAPM

Documentinformatie

Geüpload op
12 april 2026
Aantal pagina's
31
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$25.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
Excellentdocsolution

Maak kennis met de verkoper

Seller avatar
Excellentdocsolution Stanford University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
6
Lid sinds
1 jaar
Aantal volgers
1
Documenten
2098
Laatst verkocht
2 weken geleden
EXELENCE IN EDUCATIOIN

BEST AND AFFORDABLE PRICE

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen