QUESTIONS AND VERIFIED ANSWERS;
100% CORRECT; GRADE A
A licensed lp gas installer contacts a sub contractor to conduct
piping repairs at a bulk facility. the contractor? - correct
answer- must ve a licensed category 1 lp gas dealer or lp gas
installer and the license in current status
A LP gas installer who no longer possesses a Master qualifier but
currently employs a lp gas installer qualifier will have how many
days to replace master qualifier - correct answer- 60
days
A vacancy in the qualifier position of an lp gas license holder
must be reported to the department - correct answer-
No later than 1 work day following the last day of employment
according to florida law verifiable liquefied petroleum gas leaks
must be physically responded to - correct answer- within
a reasonable time not to exceed 24 hours
, an lp gas installer licensee has 15 employees 3 office staff 2 tank
installers 6 pipe installers 4 appliance installers and repair techs.
how many lp installer qualifiers is the licensee required to have?
- correct answer- 2
any container of 100 gallons or more water capacity which has
not been in use for a period of 12 months must be - correct
answer- properly abandoned in place, removed and
pressure tested every 12 months
before a LP GAS license is issued to a applicant the applicant
must? - correct answer- Proof of insurance, have Master
Q and be employed
bulk storage facilities must have all liquid and vapor piping color
coded as follows - correct answer- liquid: red, vapor
yellow, water blue
Can you have tanks on roofs in Florida - correct answer-
No
cylinders must be marked with the following information -
correct answer- serial number water capacity and tare
weight of the cylinder in pounds fitted for service