ANSWERS
2. A contracting officer may delegate conducting a post-
award orientation conference to the administrative
contracting officer (ACO).
a) True
b) False - CORRECT ANSWERS ✔✔a
3. Generally, government contracts do not hold
contractors liable for loss of government property if the
property is
provided under which type of contract?
a) Contracts for commercial products and commercial
services
b) Contracts with educational institutions
c) Cost-reimbursement contracts
d) Contracts that do not exceed the Simplified Acquisition
Threshold (SAT) - CORRECT ANSWERS ✔✔c
5. What part of the Federal Acquisition Regulation (FAR)
identifies the required contract file documentation?
,a) FAR 4.804
b) FAR 4.803
c) FAR 4.7
d) FAR 4.6 - CORRECT ANSWERS ✔✔b
6. When must a contractor maintain an approved
property management system and be monitored by a
government
property representative?
a) Never
b) Always
c) If the contractor has failed an audit
d) If the contractor has been provided government
furnished property - CORRECT ANSWERS ✔✔d
7. What process is described in the following statement?
Using the technical specifications, COR, or in plant QAS
inspects to ensure supplies/services meet contract
requirements.
a) Government quality assurance
b) Contract performance
c) Government acceptance
, d) Contractor invoice review - CORRECT ANSWERS ✔✔a
8. What contractor system includes expediting delivery of
materials?
a) Purchasing system
b) Material management and accounting system
c) Accounting system
d) Delivery management system - CORRECT ANSWERS
✔✔a
9. A contractor is allowed to rebut any part of their
performance report in the Contractor Performance
Assessment
Reporting System (CPARS) report once the government
has finalized and submitted the report.
a) True
b) False - CORRECT ANSWERS ✔✔b
10. Which statement is accurate regarding contractor
submission of cost data?
a) It is required when modifying a contract or subcontract
for commercial products or commercial services
b) It is required when a waiver has been granted