What is the most common type of dependency between activities? correct answers finish-to-start
What are the main topic areas of planning process group and scope management knowledge
area? correct answers Main topics are:
-Collect requirements
-Define Scope of project
-Create Work Breakdown Structure
-WBS Dictionary
What Is Project Scope Management? correct answers Scope - refers to all (100%) the work
involved in creating the products of the project and the processes used to create them
Project scope management includes the processes involved in defining and controlling what is or
is not included in a project
Project Scope Planning Process correct answers Collecting requirement: doing
interviews/analysis etc. to collect the potential requirements of the projects
Define Scope: reviewing the project charter, requirements documents, and organizational process
assets to create a scope statement
Creating the WBS: subdividing the major project deliverables into smaller, more manageable
components
Verifying scope
Controlling Scope
, Scope Planning Key Deliverables correct answers Define Scope: Scope Statement
Creating the WBS: WBS
Challenges of Scope Management? correct answers Scope Creep: refers to changes, continuous
or uncontrolled growth in a project's scope, at any point after the project begins.
What is a Scope Statement? correct answers A scope statement describes the characteristics of
the product that the project was created to deliver. It should include the following information:
• a project justification
• a brief description of the project's products
• a summary of all project deliverables
• a statement of what determines project success - user acceptance criteria
Methods for Collecting Requirements correct answers • Interviewing
• Focus groups and facilitated workshops
• Questionnaires and surveys
• Observation / Ethnography
• Prototyping
Work Breakdown Structure (WBS) correct answers Grouping of activities that need to be
performed in order to accomplish the scope.
WBS Dictionary and why do you need one? correct answers A document that describes detailed
information about each WBS item
Many WBS tasks are vague and must be explained more so people know what to do and can
estimate how long it will take and what it will cost to do the work