A compelling proposal should be written using clear, concise,
simple language without jargon that is not widely known or can
be misunderstood.
True
False - correct answer- True
A solicitation needs an amendment due to the government
changing its requirements. The following must be included:
Contact information for one of the potential offerors who
decided not to respond
Explanation for why the general scope of the proposed contract
action has changed, and why the original solicitation no longer
validly describes the requirement
A mandatory change of due date for submitting offers
Name and address of issuing activity, number of pages,
government point of contact and phone number - correct
answer- Name and address of issuing activity,
,number of pages, government point of contact and phone
number
According to FAR 11.002, why must agency acquisition
requirements be stated?
To promote competition
To include only necessary restrictive provisions or conditions to
the extent that satisfies the needs of the agency or as authorized
by law
To describe requirements in terms of functions to be performed,
performance required, and essential physical characteristics
All of the above. - correct answer- All of the
above
According to FAR 7.105, a written acquisition plan has two main
parts, which are:
Acquisition background and objectives, and plan of action
Competition, and cost
Performance period requirements, and source selection
procedures
, Risks, and sources - correct answer- Acquisition
background and objectives, and plan of action
After the release of the solicitation, you are in involved in an
exchange with industry involving questions about extensions on
the due date. According to FAR 15.201, which of the following
guidance is applicable?
Ensure multiple contracting officers can respond to questions as
they arise
Ensure that a request for information (RFI) is in place with the
required format
Make available to the public any information disclosed to
potential offerors as soon as practicable, but no later than the
next general release of information, to avoid an unfair
competitive advantage
None of the above - correct answer- Make
available to the public any information disclosed to potential
offerors as soon as practicable, but no later than the next
general release of information, to avoid an unfair competitive
advantage