Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

ARE 5.0 – CE Exam with all Correct & 100% Verified Answers |Latest Version |Already Graded A+

Beoordeling
-
Verkocht
-
Pagina's
11
Cijfer
A+
Geüpload op
15-04-2026
Geschreven in
2025/2026

ARE 5.0 – CE Exam with all Correct & 100% Verified Answers |Latest Version |Already Graded A+

Instelling
ARe
Vak
ARe

Voorbeeld van de inhoud

ARE 5.0 – CE Exam with all Correct & 100% Verified
Answers |Latest Version |Already Graded A+

Allowances ✔Correct Answer-Decision left for a later date
Allowances let the owner make decisions about how some amount will be spent during
construction
If what the owner ends up selecting costs more or less than the allowed amount, the contract
price adjusts automatically.
allow the architect to incorporate into the contract documents information that can't be fully
specified or drawn.

at the time the contract is signed, it's likely that no decision has been made on carpets, drapes
or decorative light fixtures. If the actual cost of finishes or equipment aren't known when the
contract is signed, include an approximate ✔Correct Answer-Allowance in the contract

at the time the contract is signed, the owner may not have picked out finishes such as flooring,
appliances or fixtures. The actual cost won't be known until the owner makes those decisions.
So just include in the contract your best guess of the cost. That is what? ✔Correct Answer-
Allowance

Alternates ✔Correct Answer-Alternate quotes when bidding a job
Alternates are like an additional bid by the same contractor. The owner can decide which offer
to accept
are a way to price options for the work so the owner can finalize the scope of work after
evaluating the bids
In addition or in lieu

If the basic quote assumes an interior wall is a partition and not load-bearing. To specifcy an
additional cost if a support beam is required for code approval, what will the contractor use to
protect himself from surprises? ✔Correct Answer-Alternate bid

The basic quotes assumes a built-up roof. Owner is till on the fence about an elastomeric roof or
a tile roof. Owner would like to have more control over the finished product adn the cost of the
job. What should contractor prepare? ✔Correct Answer-Alternate bids

Unit price ✔Correct Answer-When exact scope isn't know at the outset, price work by the
unit
Unit pricing permits an adjustment in cost to the owner when the exact volume of work isn't
known at the outset
allow the architect to incorporate into the contract documents information that can't be fully
specified or drawn.

, the amount of sheathing or flashing needed may not be known until the roofing tear-off is
done. Fine. Write a specific quantity of sheathing and flashing into your contract. Then quote a
price per square foot for either more or less than the specified quantity. The price of the job
adjusts automatically as requirements change. Contractor used what method? ✔Correct
Answer-Unit prices

an excavation contract might show a fixed price for the job, assuming 50 cubic yards of rock
have been blasted. If the job actually requires more or less than 50 cubic yards of blasting, the
contract price will be adjusted up or down based on ✔Correct Answer-Unit prices

Cost to manage, excavate, and dispose of hazardous materials, at the direction of the owner's
environmental consultant ✔Correct Answer-Allowance

Automated irrigation system at vegetated roof areas in addition to tamper-proof hose bibs
✔Correct Answer-Alternate

Earthwork materials, including base course, fill, and drainage course, as associeted with utility
installation ✔Correct Answer-Unit price

Occupance sensors in all conference rooms in lieu of standard wall switches ✔Correct
Answer-Alternate

Construction change directive ✔Correct Answer-is appropriate when a change must take
place regardless of time or cost impacts.

The contract indicates the completion time for a project is 465 calendar days, including 45 days
for weather days. Extremely bad weather delayed construction by 65 days. The contractor has
requested an extension in the number of contract days due to the extremely bad weather. What
should the architect advise the owner? ✔Correct Answer-Extend the contract by 20 days via
change order

Per AIA Document A201-2007, General Conditions of
the Contract for Construction, if the contractor is delayed by causes beyond the contractor's
control, ✔Correct Answer-then the contract time shall be extended via change order.
Ex. Weather delays are certainly outside the contractor's control.

The contractor notified the architect that the project was ready for substantial completion. The
architect inspected the work and prepared the following list of incomplete work. What must be
completed before the architect can issue the certificate of substantial completion? ✔Correct
Answer-The only item on this punchlist that prevents full use of the building is the bathtub that
doesn't drain properly.

What items can be completed after substantial completion? This is remaining work that must
not prevent the owner's use of the building. ✔Correct Answer-Paint touch ups

Geschreven voor

Instelling
ARe
Vak
ARe

Documentinformatie

Geüpload op
15 april 2026
Aantal pagina's
11
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Studyclub Yale School Of Medicine
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
49
Lid sinds
1 jaar
Aantal volgers
1
Documenten
11132
Laatst verkocht
4 uur geleden
"The Club for Top Academic Performance."

Welcome to StudyClub—the ultimate destination for students who want to make studying not only effective but also enjoyable! Whether you’re preparing for an exam, looking to improve your grades, or mastering new subjects, StudyClub is your go-to space to find the tools and resources you need to succeed. At StudyClub, I believe in the power of community. That’s why I’ve created a collection of high-quality study materials designed to simplify complex concepts and help you achieve your academic goals. Whether you’re an individual looking to study independently or a student seeking the support of a virtual study group, you’ll find everything you need to succeed. Join the StudyClub today, where learning is made easier, more organized, and—most importantly—more collaborative. Let’s grow together, learn smarter, and unlock your academic potential. Thank you for being part of the StudyClub community. I can’t wait to see you succeed!

Lees meer Lees minder
3.6

13 beoordelingen

5
6
4
1
3
3
2
1
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen