CM 2500 EXAM 2 (PART 2) – PRACTICE QUESTIONS & STEP-BY-STEP SOLUTIONS
EXAMITY PROCTORED PREP GUIDE | 2026 EDITION
• This guide pairs every question with a clearly bolded correct answer and a
detailed EXPERT RATIONALE — work each question independently first, then verify
your reasoning against the explanation to lock in deep, exam-ready understanding.
• Each question is written to mirror proctored exam style, covering all core
Construction Management topics so you can study one resource from start to finish
with full confidence.
1. Which project delivery method involves the owner contracting separately
with a designer and a general contractor?
A. Design-Build (DB)
B. Construction Manager at Risk (CMAR)
C. Integrated Project Delivery (IPD)
D. Design-Bid-Build (DBB)
E. Public-Private Partnership (P3)
✔ Correct Answer: D. Design-Bid-Build (DBB)
EXPERT RATIONALE: In Design-Bid-Build, the owner holds two separate contracts
— one with the designer and one with the general contractor. The contractor is
selected after the design is complete, typically through competitive bidding. This is
the most traditional and widely used project delivery method in public construction.
2. In a Design-Build (DB) delivery method, the owner contracts with:
,A. A designer only, who then hires the contractor
B. A contractor only, who then subcontracts the design
C. A single entity responsible for both design and construction
D. A construction manager who oversees separate design and construction
contracts
E. Multiple prime contractors, each responsible for a portion of the project
✔ Correct Answer: C. A single entity responsible for both design and
construction
EXPERT RATIONALE: In Design-Build, the owner contracts with a single entity (the
design-builder) who is fully responsible for delivering both the design and the
constructed facility. This single point of responsibility reduces owner coordination
risk and fosters design-construction integration.
3. Which project delivery method is best known for its ability to overlap
design and construction activities, thereby reducing the overall project
schedule?
A. Design-Bid-Build
B. Construction Manager as Advisor
C. Fast-Track Design-Build
D. Unit Price Contracting
E. Lump Sum Delivery
✔ Correct Answer: C. Fast-Track Design-Build
EXPERT RATIONALE: Fast-tracking in Design-Build allows construction to begin on
completed portions of the design while other portions are still being designed. This
parallel execution significantly compresses the overall project schedule but
increases the risk of rework if downstream design decisions conflict with already-
built work.
,4. In a Construction Manager at Risk (CMAR) arrangement, the CM's primary
financial risk comes from:
A. Designing the project beyond the approved budget
B. Providing a Guaranteed Maximum Price (GMP)
C. Managing subcontractors' safety records on site
D. Hiring the architect on behalf of the owner
E. Approving all shop drawings and submittals
✔ Correct Answer: B. Providing a Guaranteed Maximum Price (GMP)
EXPERT RATIONALE: In CMAR delivery, the construction manager assumes the
financial risk of a Guaranteed Maximum Price — if actual costs exceed the GMP, the
CM absorbs the overrun. Savings below the GMP are typically shared or returned to
the owner per the contract terms.
5. Which delivery method is characterized by a multi-party agreement
between the owner, designer, and contractor, with shared risk and reward?
A. Design-Bid-Build
B. Construction Manager as Advisor
C. Progressive Design-Build
D. Integrated Project Delivery (IPD)
E. Job Order Contracting (JOC)
✔ Correct Answer: D. Integrated Project Delivery (IPD)
EXPERT RATIONALE: IPD uses a multi-party agreement that aligns the interests of
the owner, designer, and contractor through shared risk and reward, collaborative
decision-making, and lean construction principles. All parties benefit from project
success and share in the consequences of poor performance.
, 6. Job Order Contracting (JOC) is most commonly used for:
A. Large, one-of-a-kind construction projects
B. Repetitive renovation and repair work at a fixed facility
C. Public-private infrastructure partnerships
D. International construction procurement
E. High-rise commercial tower construction
✔ Correct Answer: B. Repetitive renovation and repair work at a fixed facility
EXPERT RATIONALE: JOC is an indefinite delivery/indefinite quantity (IDIQ)
contracting method used primarily by facility owners to efficiently procure a stream
of small-to-medium renovation, repair, and maintenance projects without repeated
full bidding cycles. Pricing is based on a pre-established unit price book.
7. Which of the following is NOT a typical advantage of the Design-Build
delivery method?
A. Single point of responsibility
B. Faster project delivery
C. Potential for design innovation
D. Maximum owner control over design details
E. Early cost certainty
✔ Correct Answer: D. Maximum owner control over design details
EXPERT RATIONALE: One of the tradeoffs of Design-Build is that the owner gives
up some direct control over design details, since a single entity handles both design
and construction. Owners who want maximum control over every design decision
typically prefer Design-Bid-Build with detailed specifications.