Question 1
Correct 4 points out of 4
The forward pass alone in the Critical Path Method can be used to determine . Choose all
that are correct.
A. Activity early finish time
B. Activity late finish time
C. Total float
D. None of these
Your answer is correct.
, Question 2
Correct 20 points out of 20
Use the Diagramming method to answer the following questions.
1. What detail is displayed at the letter a?
Activity Duration
Consecutive Activity
Activity Description
Activity Restraint
4 points out of 4
2. What does the space denoted by the letter b represent?
Length of an Activity
Free Float
Activity Interrelationship
None of these
4 points out of 4
3. What detail is displayed at letter c?
Activity Description
Effective Days
Job Description
Activity Duration
4 points out of 4
4. What does the Vertical line with an arrowhead at d indicate?
Activity Duration
Float
Latest Start
Activity Restraint or Relationship
4 points out of 4