Branch circuit conductors within ______ inches of a ballast shall
have an insulation temperature rating not lower than ______
unless supplying a luminaire listed and marked as suitable for a
different insulation temperature.
A. °C
B. °C
C. °C
D. °C - ✔✔✔ Correct Answer > B. °C
410.68
An office service is 240/120V three-phase. The building feeder
conductor supplied by a single-phase 240/120V panel conductor
has a continuous load of 12,450VA and a non-continuous load of
16,260VA. What is the MINIMUM size of the overcurrent protective
device required?
,Page 2 of 158
A. 100A
B. 125A
C. 150A
D. 200A - ✔✔✔ Correct Answer > C. 150A
215.3
240.4
240.4(B)
240.6
1. Continuous load x 125% + non-continuous load / 240V
2. Select OCPD from 240.6
12,450VA x 1.25 = 15,575VA + 100% of 16,260VA Total = 31,835VA
31,835VA ÷ 240V = 132.6A
3. 240.4(B) "round-up to next size OCPD on 240.6 = 150 ampere
OCPD
Where one or more lighting outlets are installed for interior
stairways, there shall be a(n) _______ wall mounted control
,Page 3 of 158
device at each floor level and landing level with an entrance to
the stairway to control the lighting outlet where the stairway has
six or more risers between levels.
A. Approved
B. Listed
C. Specified
D. Engineered - ✔✔✔ Correct Answer > B. Listed
210.70(A)(2)(1)
What do you call a branch circuit where there are two or more
ungrounded conductors that have a voltage between them, and a
grounded conductor that has equal voltage between it and each
ungrounded conductor of the circuit and that is connected to the
neutral or grounded conductor of the system?
A. appliance branch circuit
B. general-purpose branch circuit
C. individual branch circuit
D. multiwire branch circuit - ✔✔✔ Correct Answer > D. multiwire
branch circuit
, Page 4 of 158
100 (Definitions): Branch Circuit, Multi-wire
What is the feeder demand for five 10 kW ranges installed in a
dwelling unit?
A. 20 kW
B. 12 kW
C. 22.5 kW
D. 50 kW - ✔✔✔ Correct Answer > A. 20 kW
Table 220.55 (Column C)
Column C for 5 ranges is 20 kW
A 75-site mobile home park is designed for mobile homes that
have 14,000 VA load per site. What is the feeder/service
calculated load for the mobile home park that has a system is
120/240V, single phase?
A. 1,200 kVA
B. 264 kVA
C. 222 kVA