DBIA Certification ACTUAL EXAM QUESTIONS AND
CORRECT DETAILED ANSWERS LATEST UPDATE THIS
YEAR
Exam Coverage – DBIA Certification Exam
The DBIA certification exam measures mastery of design-build best practices and their
application across the entire project lifecycle . The exam consists of 100 questions with a 2-hour
time limit; passing score is 72% . Content domains include: Guiding Principles (8%) – ethical
conduct, competence, diversity, professional development; Foundations of Design-Build Done
Right (8%) – core concepts, integration, single-point responsibility; Procuring Design-Build
Services (30%) – RFQ/RFP processes, best value selection, shortlisting, qualifications-based
evaluation; Contracting for Design-Build Services (24%) – contract formats (lump sum, GMP,
cost-plus), teaming agreements, risk allocation, Spearin Doctrine, indemnification; Executing
Design-Build Projects (30%) – design management, quality assurance/control, trend
management, closeout, commissioning, collaboration .
200 Randomized, Scenario-Based MCQs for DBIA Practice Test
1. A public owner is considering design-build for a new wastewater treatment plant. What is the
most important initial step before selecting this delivery method?
A) Prepare full design drawings to save time later
B) Conduct a proactive assessment of project characteristics and organizational readiness
C) Hire a contractor immediately to begin preconstruction
D) Issue a request for proposals without any planning
Answer: B
RATIONALE: Owners must conduct a proactive and objective assessment of project
characteristics and organizational needs before selecting design-build to ensure it is the right
fit .
, Page 2 of 94
2. A design-build team is formed through a joint venture between an architectural firm and a
construction company. What document should they execute before submitting a proposal?
A) Construction contract with the owner
B) Teaming agreement defining their temporary partnership
C) Performance bond for the full project value
D) Design management plan only
Answer: B
RATIONALE: Teaming agreements form temporary partnerships between design and
construction firms before project award, defining roles and responsibilities during proposal
preparation .
3. An owner wants to select a design-build team based on qualifications first, then evaluate
technical approaches and price only from shortlisted firms. What procurement method is being
described?
A) Low-bid procurement
B) Two-phase selection with RFQ then RFP
C) Sole source procurement
D) Construction manager at risk
Answer: B
RATIONALE: Two-phase selection involves Phase 1 (RFQ for qualifications) to shortlist teams,
followed by Phase 2 (RFP) for technical and price proposals from shortlisted firms .
, Page 3 of 94
4. A design-build contract includes a clause requiring the contractor to pay $5,000 for each day
the project is delayed beyond the scheduled completion date. What type of damages is this?
A) Consequential damages
B) Punitive damages
C) Liquidated damages
D) Nominal damages
Answer: C
RATIONALE: Liquidated damages are predetermined, reasonable compensation for schedule
delays that provide predictable remedies without requiring proof of actual loss .
5. During a design-build project, the owner wants to see all cost information including
contingency reserves and subcontractor pricing. What financial management approach enables
this transparency?
A) Closed-book accounting
B) Open-book accounting
C) Fixed-price lump sum only
D) Cost-plus-percentage fee
Answer: B
RATIONALE: Open-book accounting promotes transparency and trust in cost management,
reflecting DBIA's collaborative culture of shared financial visibility .
6. A contractor relied on an owner's verbal promise to extend the project schedule and incurred
significant costs preparing for the new timeline. The owner later denied making the promise.
, Page 4 of 94
What legal theory might protect the contractor?
A) Spearin Doctrine
B) Promissory estoppel
C) Miller Act
D) Brooks Act
Answer: B
RATIONALE: Promissory estoppel allows courts to enforce a promise even without a formal
written contract when a party has reasonably relied on that promise to their detriment .
7. An owner provides the design-builder with prescriptive specifications for a mechanical
system. The system fails due to a design defect in the owner's specifications. Under the Spearin
Doctrine, who is typically liable?
A) The design-builder only
B) The owner who furnished the defective specifications
C) The subcontractor who installed the system
D) The architect of record only
Answer: B
RATIONALE: The Spearin Doctrine holds that an owner implicitly warrants that prescriptive
plans and specifications are suitable and is liable for defects in those furnished documents .
8. A design-build team is evaluating potential projects to pursue. According to DBIA guidance,
what type of owner should they be cautious about working with?
A) Owners with experienced design-build staff