Which Incident Type requires one or two single resources with up to six
personnel? - CORRECT ANSWER -Type 5
Which of the following would NOT typically be included in the transfer of
command briefing? - CORRECT ANSWER -Special requests from agency
representatives
An Incident Commander's scope of authority comes from the Incident Action
Plan. - CORRECT ANSWER -False
Which Incident Type requires or national resources with up to 200 personnel
per operational period? - CORRECT ANSWER -Type 2
Which of the following best describes the Operational Period Briefing? -
CORRECT ANSWER Helps keep the public and media informed about the
incident status and operational accomplishments.
Who generally facilitates the Operational Period Brief? - CORRECT ANSWER -
Planning Sectional Chief
Which major NIMS component describes systems and methods that help to
ensure that incident personnel and other decision makers have the means
and information they need to make and communicate decisions? - CORRECT
ANSWER -Communications and Information Management
Mutual Aid Agreements - CORRECT ANSWER -Assist agencies and
jurisdictions when existing resources are inadequate.
NIMS-IS 200.
, Which of the following is NOT part of the NIMS Management characteristic of
Chain of
Command? - CORRECT ANSWER -Restricts personnel from sharing
information with each other.
Which General Staff member directs management of all incident-related
operational activities to achieve the incident objectives? - CORRECT ANSWER
-Operations Section Chief
Staff-level briefings are conducted by the supervisor to introduce co-workers,
clarify tasks, define the scope of work, describe sources of work supplies, and
present the work schedule. - CORRECT ANSWER -True
Which NIMS Management Characteristic helps to eliminate confusion caused
by multiple, conflicting directives? - CORRECT ANSWER -Chain of Command
and Unity of Command
ICS Form 201 is not suitable for use as an initial Incident Action Plan (IAP). -
CORRECT ANSWER False
Which Incident Type do these characteristics describe: some or all of the
Command and General Staff are activated as well as Division or Group
Supervisor and/or Unit Leader positions, the incident extends into multiple
operational periods, and a written IAP is required? - CORRECT ANSWER -Type
3
The process of granting authority to carry out specific functions is called -
CORRECT ANSWER Delegation of Authority
Which statement below correctly describes how to manage span of control
using the modular concept? - CORRECT ANSWER -Span of control is
NIMS-IS 200.