New York Crane Operator Licensing Exam ACTUAL
VERIFIED EXAM COMPLETE QUESTIONS AND
CORRECT ANSWERS LATEST UPDATE THIS
YEAR.pdf||NEWEST EXAM!!
According to OSHA, a crane shall be equipped with a
boom angle indicator, a device to indicate boom extended
length, and a _______ - Answer-anti-two-block device
If the rotation-resistant rope is used, the slings must be
capable of supporting, without failure, at least ______
times the maximum load. - Answer-10
According to ASME, periodic inspections of platforms are
to be conducted at least once every ______ months -
Answer-12
Hooks on overhaul ball assemblies, lower load blocks, or
other attachment assemblies must be _______. - Answer-
Permanently Mounted
Wire rope, shackles, rings, master links, and other rigging
hardware must be capable of supporting, without failure, at
,2|Page
least ______ times the maximum intended load applied or
transmitted to the component. - Answer-5
If deficiencies are found and corrected on a platform after
a proof test has been conducted, _________. - Answer-
another proof test needs to be conducted.
Under ASME guidelines, the inspection paperwork for the
last inspection preformed on a platform is to be
kept______. - Answer-with the platform
A full-body harness lanyard must have a maximum length
that allows a fall to go no greater than _____ feet. -
Answer-6
A live boom is a boom in which_______. - Answer-
lowering is controlled by a brake without aid from other
devices that slow the lowering speed
If a personnel platform includes a perforated steel
enclosure, the perforations must be no greater
than________ inch. - Answer-1/2
, 3|Page
The toe board on a personnel lifting platform must be
installed______of the platform. - Answer-around the entire
perimeter
The personnel platforms rigging may only be used for the
platform, employees, tools and ______ - Answer-Materials
For hoisting operations, the crane must be level; within
_____ percent, with outriggers fully developed per
manufacturers specifications. - Answer-1
During proof testing, the platform and rigging are required
to be loaded to _____ percent of the platforms rated
capacity. - Answer-125
According to OSHA 1926.1431, all eyes in wire rope slings
must be fabricated with ______ - Answer-thimbles
Under both OSHA and ASME guidelines, the platform
must be held______ minutes during proof testing. -
Answer-5