Who is responsible for issuing clearances ? - Answer- Power Director
What must be done immediately after testing of a circuit is performed ? - Answer-
Report results to the power director
When can a Class " A " employee operate a switch ? - Answer- After receiving
permission from the Power Director
What is the Red Tag number ? - Answer- NEC 105
What is the proper grounding technique after receiving a favorable test ? - Answer-
Secure the earth clamp , attach the ground to the conductor
What must be done before touching wire in an electrified territory ? - Answer- Test de -
energized , receive clearance and ground
How often will rubber gloves be electrically tested ? - Answer- 60 days
Defective tools should be - Answer- tagged and removed from service
A file or a rasp should be - Answer- used with a handle
What is the voltage rating of the rubber gloves purchased by Amtrak's Electric Traction
Department ? - Answer- 20,000 volts
What form of rigging allows for a sling to be used at its maximum strength ? - Answer-
Basket
How should tools and materials be placed in order to follow safe Amtrak procedures ? -
Answer- Placed so as not to create a tripping hazard
What are the three sizes of hoists commonly used in line work ? - Answer- 1½ , 3 and 6
ton
What P.P.E. ( Personal Protective Equipment ) should be worn when pulling material up
a pole with a handline ? - Answer- Hard hat , glasses , gloves
What are the most common sizes of blocks used ? - Answer- 4 " and 5 "