Question 1
A designer is programming a 5,000 sq ft corporate office.
Which information is MOST critical to collect first?
A) Color preferences of the CEO
B) Number of employees and their work patterns
C) Budget for furniture
D) Preferred furniture vendors
Correct Answer: B
Rationale: Programming begins with understanding user
,Page 2 of 195
needs, headcount, and how space will be used. Aesthetics and
vendors come later in the design process.
Question 2
During schematic design, the client requests a change that
increases square footage by 20%. What should the designer
do FIRST?
A) Redraw all floor plans
B) Inform the client of potential budget and schedule impacts
C) Hire a contractor
D) Proceed without discussion
Correct Answer: B
Rationale: Designers must manage scope changes
transparently. Budget and schedule impacts must be
communicated before proceeding with redesign.
Question 3
What is the correct order of design phases?
A) Programming → Schematic Design → Design Development
,Page 3 of 195
→ Construction Documents → Construction Administration
B) Schematic Design → Programming → Design Development
→ Construction Documents → Construction Administration
C) Programming → Design Development → Schematic Design
→ Construction Documents → Construction Administration
D) Design Development → Programming → Schematic Design
→ Construction Documents → Construction Administration
Correct Answer: A
Rationale: Standard NCIDQ sequence: Programming (define
problem), SD (initial solutions), DD (refine), CD (technical
drawings), CA (implementation).
Question 4
A client wants to see three different space planning options.
Which phase is this?
A) Programming
B) Schematic Design
, Page 4 of 195
C) Design Development
D) Construction Documents
Correct Answer: B
Rationale: Schematic Design is where multiple layout
alternatives are explored. Design Development refines a
single chosen option.
Question 5
In which phase does the designer select specific light fixtures,
finishes, and furniture models?
A) Programming
B) Schematic Design
C) Design Development
D) Construction Administration
Correct Answer: C
Rationale: Design Development involves finalizing material
and product selections. CD is for technical drawings; CA is
during construction.