CORRECT EXAMS
what is project over head - answer-items needed to
complete the project ex; bonds,temporary
storage,dumpsters,security guards , porter
potties,etc. makes up 5-10% of bid
what is the clean water act - answer-establishes
the basic structure for regulating disharges of
pollutants into the waters of united states
how many employees are you required to have in
order to have works comp? - answer-more than 1
employee
if you fail to identify and mark underground utilities,
how much do you have to pay for violation -
answer-you can be fined up to 5000 dollars for the
first violation, and up to 70000 dollars
, sets limits on how much of a air pollutant is allowed
in the air. - answer-the clean air act
when does the fair labor act apply - answer-it
applies to employers that have 1 or more employee
what is form I-9 - answer-this form is used by
immigration ,to make sure employees has legal
immigration status in the usa
what are current liabilities - answer-liabilities that
will mature and must be paid within 1 year
immigration forms must be kept for how long -
answer-at least 3 years
what is a maintance bond - answer-guarantees that
for one year no defective workmanship or material
will appear on completed project