The _________ consists of daily checks of the work to assure continuing compliance with contract
requirements - CORRECT ANSWER - Follow-up Phase
Design-Build contracts require - CORRECT ANSWER - The QC Manager to be in place and take
an active role in the review and coordination of the design.
Which of the following is included in all three phases of the Three Phases of Control? - CORRECT
ANSWER - Safety
The purpose of Construction Quality Management is to - CORRECT ANSWER - Achieve the
quality established by properly developed requirements through the combined responsibility, but separate,
efforts of contractors and government personnel
Testing is extremely important in construction quality management and is performed by - CORRECT
ANSWER - Both the contractor and the government
The primary purpose of the Three-Phase Control System is to - CORRECT ANSWER - Require
the contractor to plan, schedule, and perform quality management actions to assure work meets all
specified quality standards
Quality Assurance Personnel have the responsibility to - CORRECT ANSWER - Require the
contractor to maintain the quality specified in the plans and specifications
The _________________ is the appropriate time to assure that all materials and/or equipment have been
tested, submitted, and approved - CORRECT ANSWER - Preparatory Phase
, The Preconstruction Conference and Coordination and Mutual Understanding Meeting Are - CORRECT
ANSWER - Conducted prior to the commencement of any physical construction work
Contractor testing procedures: - CORRECT ANSWER - Are specified in the technical specs,
outlined in the QCP, and addressed at Coordination and Mutual Understanding Meeting
The Quality Control Plan contains - CORRECT ANSWER - Identification of individual quality
quality control personnel, including name, qualifications, assigned duties, responsibilities and authorities.
Tests that are unannounced, randomly performed, and repeat quality control tests are - CORRECT
ANSWER - Quality assurance tests
The contractor is required to conduct a Preparatory Phase Meeting before they begin any definable feature
of work except when - CORRECT ANSWER - There are no exceptions to the rule
During the punch-out inspection of a project: - CORRECT ANSWER - Quality Control personnel
prepare and punch-list and make corrections
The Quality Control Report should include - CORRECT ANSWER - All of the above
In a design build contract, if the contractor has a question about the design, what is the process to get an
answer? - CORRECT ANSWER - Contractor submits a design verification request to the
contractor's design team
Submittals are - CORRECT ANSWER - Necessary to demonstrate that the proposed materials, etc.
are in compliance with the contract.
The success or failure of all contractors is based upon - CORRECT ANSWER - The ability to
control costs, finance work, estimate jobs, schedule the work and maintain effective quality control
The contract requires the contractor to submit quality control reports - CORRECT ANSWER -
Daily