BC Electrical Field Safety Representative (FSR) Class A Exam
ACTUAL EXAM COMPLETE QUESTIONS AND CORRECT
ANSWERS LATEST UPDATE THIS YEAR
BC Electrical Field Safety Representative (FSR) Class A Exam
Technical Safety BC
ACTUAL EXAM COVERAGE (FULL CONTENT AREAS)
1. BC Electrical Safety Regulation
• Safety standards under BC Safety Standards Act
• Electrical installation rules and compliance duties
• Responsibilities of licensed contractors and FSRs
2. Canadian Electrical Code (CEC)
• Rule application and interpretation
• Wiring methods and conductor sizing
• Grounding and bonding requirements
• Protection devices (breakers, fuses, GFCI, AFCI)
3. Inspection & Authorization
• Field inspection procedures
• Permit verification and authorization to energize
• Deficiency reporting and correction orders
4. Electrical Installations
• Residential, commercial, industrial systems
• Services, feeders, branch circuits
• Equipment approval requirements
5. Hazard Identification & Safety
• Shock and arc flash hazards
• Lockout/tagout procedures
• Safe work practices and PPE
6. Documentation & Compliance
• Safety reports
• Inspection records
• Code violation documentation
7. Enforcement Powers of FSR A
• Issuing orders
• Stopping unsafe work
• Compliance escalation
1.
A contractor requests authorization to energize a newly installed commercial panel without completed
grounding verification. What should the FSR do?
, Page 2 of 104
A. Approve immediately
B. Deny energization until grounding compliance is verified
C. Ignore requirement
D. Reduce inspection scope
Answer: B
Rationale: Energization cannot be approved without confirmed grounding compliance under CEC rules.
2.
During inspection, an FSR finds undersized conductors feeding a high-load HVAC system. What is the
correct action?
A. Approve installation
B. Issue correction order before energization
C. Ignore if system runs
D. Reduce breaker size only
Answer: B
Rationale: Undersized conductors create fire risk and violate CEC ampacity rules.
, Page 3 of 104
3.
A site contractor bypasses permit requirements and begins electrical installation work. What is the FSR’s
authority?
A. Ignore
B. Issue stop-work order immediately
C. Reduce inspection scope
D. Approve retroactively
Answer: B
4.
An inspection reveals missing bonding on metal conduit systems. What is the primary hazard?
A. Efficiency loss
B. Electric shock risk due to fault current path failure
C. Lighting failure
D. Overheating only
Answer: B
, Page 4 of 104
5.
A panelboard has multiple breakers not labeled correctly during inspection. What is required?
A. Approve system
B. Require proper circuit identification before approval
C. Ignore labeling
D. Reduce load
Answer: B
6.
A contractor requests approval to energize equipment without completing insulation resistance testing.
What should the FSR do?
A. Approve
B. Require testing before energization
C. Ignore
D. Reduce voltage
Answer: B