EEA Level 1 ✔Correct Answer-All available resources in use.
Max Gen Emergency Alert
EEA Level 2 ✔Correct Answer-Emergency Mandatory Load Management Reductions Action,
Voltage Reduction Action, Deploy All Resources
EEA Level 3 ✔Correct Answer-Manual Load Dump Action
Unit Startup Notification Alert ✔Correct Answer-Place Gen Units in state of readiness to be
online w/in 48 hrs.
Unit Startup Notification Alert Triggers ✔Correct Answer-In anticipation of operating capacity
shortage, stability issues or constrained operations. When long lead time generation is needed
for a future period.
Unit Startup Notification Alert "State of Readiness" ✔Correct Answer-The lesser of: notify
time + startup time - 48 hours or 6 days - 48 hours
able to be online w/in 48 hours
Max Gen/Load Management Alert ✔Correct Answer-Operating Reserve Requirement is
greater than scheduled Operating Reserve
Issued 1 or more days out.
Primary Reserve Alert ✔Correct Answer-Estimated Operating Reserve Capacity is less than
forecasted Primary Reserve requirement.
Primary Reserve Alert Member Actions ✔Correct Answer-Notify management, stations and
key personnel.
Review plans to determine deferral of maintenance, testing, etc.
Inform PJM of environmentally restricted units
Voltage Reduction Alert ✔Correct Answer-Est. Operating Reserve Capacity is less than
forecasted Synchronized Reserve requirement.