WGU C722 Project Management Pre-assessment Actual Exam (Latest 2026 Update) – Complete Questions and Correct Verified Answers/ C722 Pre-assessment Test| Already Graded A+

Beoordeling
-
Verkocht
-
Pagina's
92
Cijfer
A+
Geüpload op
21-04-2026
Geschreven in
2025/2026

WGU C722 Project Management Pre-assessment Actual Exam (Latest 2026 Update) – Complete Questions and Correct Verified Answers/ C722 Pre-assessment Test| Already Graded A+

Instelling
WGU C722
Vak
WGU C722

Voorbeeld van de inhoud

WGU C722 Project Management Pre-assessment Actual Exam
(Latest 2026 Update) – Complete Questions and Correct Verified
Answers/ C722 Pre-assessment Test| Already Graded A+
A firm begins its strategic business initiative of developing a new
business model that will allow the firm to deliver an efficient, tailored
service to its customers. To accomplish this, the firm initiates a
business management project. Which aspect of project management
applies to this firm's project? - Answer -Interdependent Tasks


A firm begins its strategic business initiative of developing a new
business model to enhance its competitiveness. What can be identified
as a strategic business initiative for this firm? - Answer -Improvement
in product design


A firm begins a strategic business initiative of developing a new
business model that will allow the firm to deliver an efficient, tailored
service to its customers. - Answer -Project sponsor


Which group is included in the five process groups? - Answer -
Closing process group


What does PRINCE2 stand for? - Answer -PRojects IN a Controlled
Environment


Which PMBOK process group is described as the delivery part of
project management where the main activity happens? - Answer -
Executing




pg. 1

,Which advantage does the functional (departmentalized)
organizational structure provide for a firm with multiple projects? -
Answer -Lines of authority are clear.


Which two organizations are examples of organizations with the
functional organizational structure? - Answer -(1) The U.S.
Department of State and (2) The U.S Department of Energy


An organization expects to use a project management office (PMO) to
support multiple projects that will be implemented within a
projectized organizational structure. Which implied effect is a benefit
to this organization? - Answer -Project team members gain access to
historical data from other projects.


Regardless of the organizational structure used to manage a project,
an organization elects to use a project management office (PMO).
Which benefit will this organization gain? - Answer -Projects will
coordinate resource usage by monitoring the status of shared
resources.


During a certain project phase, specific blueprints are drawn and
approved, materials and labor costs are estimated, prototypes are
created, and work activities and tasks are identified. Also, quality
expectations, measurements, and costs are defined. During which
project phase do these activities occur? - Answer -Planning


Place the project activities in order of occurrence from first (1) to last
(5). - Answer - (1) Collecting customer requirements (2) Developing
the work breakdown structure (3) Working to produce project
deliverables (4) Customers evaluating the project outcomes (5)
Capturing lessons learned

pg. 2

,During which life cycle phase is the vast majority of the actual work
to produce the project's deliverables completed? - Answer -Executing


What is the correct term for an intermediate outcome of project work,
such as a signed contract or obtaining a construction permit? - Answer
-Deliverable


Which deliverable from a work breakdown structure (WBS) is not
specific enough to measure its completion at project closure? -
Answer -User training


The following table shows the Level 1 work breakdown structure
(WBS) for Project A.
WBS ID Description
0.0 Project A
1.0 Project started
2.0 Feasiblity
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
Which approach did the project manager use to structure the WBS? -
Answer -Sequence of project phases




pg. 3

, For the following collapsed work breakdown structure (WBS) for
Project O, the project manager must complete the scope baseline. In
addition to the WBS, the scope baseline will contain two additional
documents.
WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
What are the other two documents that belong in the scope baseline? -
Answer -WBS dictionary and project scope statement


For the following collapsed work breakdown structure (WBS) for
Project O, the project's steering committee held a phase gate review of
the Feasibility results. That review determined that the project's
proposed design would be obsolete before it would reach the
marketplace.
WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development


pg. 4

Geschreven voor

Instelling
WGU C722
Vak
WGU C722

Documentinformatie

Geüpload op
21 april 2026
Aantal pagina's
92
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$17.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
SCHOLAREXAMHUB

Maak kennis met de verkoper

Seller avatar
SCHOLAREXAMHUB Walden University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
-
Lid sinds
2 maanden
Aantal volgers
0
Documenten
97
Laatst verkocht
-

Scholar Exam Hub Provides reliable and well-structured exam preparation materials designed to support students in academic success. Our resources include carefully organized study notes, revision guides, and practice exam questions and answers that simplify learning and strengthen understanding of key topics. We are committed to help students prepare effectively and perform confidently in their exams.

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen