Give this one a try later!
the degree to which a set of inherent characteristics fulfill requirements
What is free slack?
Give this one a try later!
difference between the earliest time an activity can begin and the latest
time an activity can begin without changing the completion date of any
successor task
,What is project schedule fast tracking?
Give this one a try later!
accomplishes tasks in parallel or overlapping them
What are the primary uses for schedule development?
Give this one a try later!
- to determine the start and end date of the project
- determines planned start and completion dates for each activity listed on
the WBS
True/False: Risk identification is a one time process.
Give this one a try later!
False | continuous process
What is the key to running a successful brainstorming session?
Give this one a try later!
, to foster an atmosphere that allows all ideas to be spoken regardless of
likelihood
What is the system analogy technique for activity estimation?
Give this one a try later!
- bases a current work package time estimate on the actual time of a work
package from a similar project already completed
- "top-down" approach
What is the PDSA cycle?
Give this one a try later!
plan, do, study, and act
What four development phases make up advanced COCOMO II?
Give this one a try later!
- requirements
- product design
- detailed design
- code/test development
, What is the probability and impact matrix?
Give this one a try later!
aids project team in prioritizing which risks need more attention based on
either their probability of occurring or the size of the impact to the project
or both
What is a buffer?
Give this one a try later!
additional time to complete a task
What is the capability maturity model integrated (CMMI)?
Give this one a try later!
quality of a system is highly influenced by the quality of the process used
to acquire, develop, and maintain it
What is quantitative risk analysis?
Give this one a try later!