inventories can be achieved by utilizing:
a. Total productive maintenance
b. A kanban pull system
c. The visual factory
d. Appropriate operator training records
Give this one a try later!
b. A kanban pull system
Which of the following are DFSS techniques?
a. IDOV and DMADV
b. Kaizen and kanban
,c. SPC and CWQC
d. DPIVs and KPOVs
Give this one a try later!
a. IDOV and DMADV
IDOV and DMADV are DFSS techniques. The other answer choices are
different tools.
A value stream map would normally provide data on:
a. Changeover and cycle times
b. Color coding techniques
c. Measurement system analysis
d. Supplier's finished goods inventory
Give this one a try later!
a. Changeover and cycle times
When plotting a multi-vari chart on graph paper, what metric is used for the vertical
scale?
a. Time
b. Count data
c. Variable data
d. Percentages
Give this one a try later!
c. Variable date
,What design structure uses the following four main phrases in the design process?
Clarify the task, develop a conceptual design, refine the design, generate the final
detailed design:
a. Set-based design
b. Pugh analysis
c. Critical parameter design
d. Systematic design
Give this one a try later!
d. Systematic design
The question is describing the step-by-step German methodology known
as systematic design.
Refer to the Venn diagram below: If the probability of event A is 20%, the probability
of event B is 30%, and the probability of A intersecting event B is 8%, what is the
probability of neither event?
a. 58%
b. 56%
c. 48%
d. 44%
Give this one a try later!
a. 58%
The basic statistical principle in EVOP is:
a. The ability to recognize small differences through large sample sizes
b. Operating with low levels of confidence
, c. Making large changes in independent variables
d. Determining dome contours
Give this one a try later!
a. The ability to recognize small differences through large sample sizes
Understanding, controlling, and improving an organization's processes to create
value for all stakeholder's would be called:
a. The SIPOC diagram
b. Process performance metric
c. Business process management
d. The establishment of KPIVs and KPOVs
Give this one a try later!
c. Business process management
A company struggling with low performance in terms of quality, profitability, and
productivity is considering Six Sigma initiative. A decision to proceed would be
considered:
a. Smart, they have a lot of low lying fruit
b. Unwise, they probably can't afford the effort
c. Unwise, they need to attend to basic activities first
d. Smart, they obviously need the Six Sigma structure
Give this one a try later!