A team is developing the project charter and is determining the valuable inputs used for
completing the project. The input(s) that the team should least likely consider when developing
the project charter would be the: ✔Correct Answer-Project Management Plan
In order to complete the finished attic remodel project on time, Brian decides to hang the
ceiling fan while Petrina paints the walls. This is an example of schedule: ✔Correct Answer-
Fast Tracking
Tammy is a construction project manager. The stakeholders for this neighborhood project
require the neighborhood be built within city limits so the end users will have city water. This
requirement would be listed under what section in the project scope statement? ✔Correct
Answer-Project Constraints
The project manager would like to determine the aggregate estimated costs from the individual
work packages to create a detailed breakdown of projected costs. In which process is the
project manager most likely participating? ✔Correct Answer-Determine Budget
Liz looks at the activity costs that must be incurred to complete all project deliverables. Liz is
determining the: ✔Correct Answer-Project Funding Requirements
Emily is adding a garden to her yard. She estimates the work to build a raised garden will be
$250 per day and will take six days to complete. What is the project's budget at completion?
✔Correct Answer-$1,500
A project manager has discovered that a project is outside the original scope. The project
manager has requested a change to bring expected future performance of the project work
back in line with the project management plan. What type of change implementation has the
project manager requested? ✔Correct Answer-Corrective Action
Jen is a construction project manager. Her current project has been halted due to a shortage in
the demand for housing. The housing shortage impact on the success of the project can be
referred to as: ✔Correct Answer-enterprise environment factors
Which activity must happen before a project can officially close? ✔Correct Answer-The
customer has to formally accept the final product.
Felicia is an event project manager. She is meeting with her conference stakeholders to ensure
the scope of products delivered aligns with what was planned for in the scope baseline of the
project. Which process is Felicia conducting? ✔Correct Answer-Control Scope