SCMN 3730 EXAM 2 NEWEST ACTUAL EXAM COMPLETE 100 QUESTIONS AND
CORRECT DETAILED ANSWERS/NEWEST UPDATE!!!
Question 1
What are the primary obstacles preventing the creation of "complete" contracts in supply
management?
A) Low interest rates and excessive supplier competition
B) High transaction costs and high enforcement/verification costs
C) Lack of legal precedents in the Uniform Commercial Code
D) The refusal of suppliers to use digital signatures
E) Excessive government oversight and environmental regulations
Correct Answer: B) High transaction costs and high enforcement/verification costs
Rationale: Complete contracts attempt to cover every possible contingency. However, the
cost of identifying all possibilities (transaction costs) and the cost of monitoring and
proving compliance for every detail (enforcement/verification costs) make them practically
impossible for most business relationships.
Question 2
Which contractual mechanism is considered the most basic and easiest to implement?
A) Fixed price with incentives
B) Cost plus fixed fee
C) Firm fixed price
D) Time and materials
E) Fixed price with escalation
Correct Answer: C) Firm fixed price
Rationale: Firm fixed price (FFP) is the simplest contract type because the price stated in
the agreement does not change, regardless of the supplier’s actual costs or market
fluctuations.
Question 3
In a Firm Fixed Price (FFP) contract, who bears the greatest financial risk in a rising market
(where costs increase)?
A) The buyer
B) The federal government
C) The third-party mediator
D) The supplier
E) Both parties share the risk equally
Correct Answer: D) The supplier
Rationale: Because the price is locked, if the supplier's costs for materials or labor rise, they
cannot pass those costs to the buyer. This reduces the supplier's profit margin.
Question 4
In a Firm Fixed Price (FFP) contract, who assumes the financial risk in a declining market?
, 2
A) The supplier
) The buyer
C) The agent of the supplier
D) The local court system
E) No one assumes risk in a declining market
Correct Answer: B) The buyer
Rationale: If market prices for a commodity drop significantly, the buyer is still obligated to
pay the higher, previously agreed-upon firm fixed price, thereby losing the opportunity to
save money.
Question 5
When is a "Fixed price with escalation" contract most appropriate?
A) For one-time spot purchases of office supplies
B) For short-term contracts under 30 days
C) For longer-term contracts where costs are likely to increase or decrease
D) When the supplier refuses to provide a cost breakdown
E) When the buyer wants to assume all financial risk
Correct Answer: C) For longer-term contracts where costs are likely to increase or decrease
Rationale: Escalation clauses allow for price adjustments (up or down) based on changes in
specific costs, which provides a safety net for both parties during long-term agreements.
Question 6
To ensure fairness, an escalation clause in a contract should ideally be tied to:
A) The supplier’s internal accounting reports
B) The buyer’s quarterly profit margins
C) An independent, published third-party index
D) The current interest rate of the Federal Reserve
E) A verbal agreement between the two CEOs
Correct Answer: C) An independent, published third-party index
Rationale: Using a neutral, third-party index (like the Consumer Price Index or a specific
commodity index) prevents either party from manipulating the price and ensures the
adjustment reflects true market conditions.
Question 7
Which contract type is best used when parties cannot accurately predict costs and quantities at
the start and agree to adjust the price at a predetermined future time based on actual experience?
A) Firm fixed price
B) Fixed price with redetermination
C) Time and materials
D) Cost plus fixed fee
E) Spot contract
, 3
Correct Answer: B) Fixed price with redetermination
Rationale: Redetermination contracts use a "best guess" base price and require a formal
review at a later date to adjust the price to reflect the actual cost experience of the supplier.
Question 8
How does a "Fixed price with incentives" contract typically function?
A) The buyer provides a gift to the supplier for finishing on time
B) The supplier is reimbursed for all costs plus a 100% markup
C) Terms allow for cost-savings sharing between the buyer and supplier
D) The price is determined by a random lottery
E) The supplier is penalized for every day the project is late
Correct Answer: C) Terms allow for cost-savings sharing with supplier
Rationale: Incentive contracts motivate suppliers to be efficient by allowing them to keep a
portion of the savings if they complete the work for less than the target cost.
Question 9
Under what conditions are "Fixed price with incentives" contracts typically utilized?
A) Low unit cost and short lead times
B) High unit cost and relatively long lead times
C) Non-critical items like paper clips
D) When the supplier has a monopoly
E) Only during international global sourcing
Correct Answer: B) Typically utilized under conditions of high unit cost and relatively long
lead times
Rationale: High costs and long durations provide enough room and time for the supplier to
find efficiencies that justify the administrative complexity of an incentive-based agreement.
Question 10
A "Cost plus incentive fee" contract is most appropriate when:
A) The parties have no idea what the final cost will be
B) The parties are confident of the initial target cost
C) The buyer wants to pay as little as possible without regard for quality
D) The supplier is in financial distress
E) The contract is for a simple commodity purchase
Correct Answer: B) Appropriate when parties are confident of initial target cost
Rationale: This contract is similar to the fixed-price version but focuses on allowable costs.
Confidence in the target cost allows the incentive structure to be meaningful and fair.
Question 11
In a "Cost-sharing" contract, what is the most critical requirement for success?
A) The use of a "not to exceed" amount
CORRECT DETAILED ANSWERS/NEWEST UPDATE!!!
Question 1
What are the primary obstacles preventing the creation of "complete" contracts in supply
management?
A) Low interest rates and excessive supplier competition
B) High transaction costs and high enforcement/verification costs
C) Lack of legal precedents in the Uniform Commercial Code
D) The refusal of suppliers to use digital signatures
E) Excessive government oversight and environmental regulations
Correct Answer: B) High transaction costs and high enforcement/verification costs
Rationale: Complete contracts attempt to cover every possible contingency. However, the
cost of identifying all possibilities (transaction costs) and the cost of monitoring and
proving compliance for every detail (enforcement/verification costs) make them practically
impossible for most business relationships.
Question 2
Which contractual mechanism is considered the most basic and easiest to implement?
A) Fixed price with incentives
B) Cost plus fixed fee
C) Firm fixed price
D) Time and materials
E) Fixed price with escalation
Correct Answer: C) Firm fixed price
Rationale: Firm fixed price (FFP) is the simplest contract type because the price stated in
the agreement does not change, regardless of the supplier’s actual costs or market
fluctuations.
Question 3
In a Firm Fixed Price (FFP) contract, who bears the greatest financial risk in a rising market
(where costs increase)?
A) The buyer
B) The federal government
C) The third-party mediator
D) The supplier
E) Both parties share the risk equally
Correct Answer: D) The supplier
Rationale: Because the price is locked, if the supplier's costs for materials or labor rise, they
cannot pass those costs to the buyer. This reduces the supplier's profit margin.
Question 4
In a Firm Fixed Price (FFP) contract, who assumes the financial risk in a declining market?
, 2
A) The supplier
) The buyer
C) The agent of the supplier
D) The local court system
E) No one assumes risk in a declining market
Correct Answer: B) The buyer
Rationale: If market prices for a commodity drop significantly, the buyer is still obligated to
pay the higher, previously agreed-upon firm fixed price, thereby losing the opportunity to
save money.
Question 5
When is a "Fixed price with escalation" contract most appropriate?
A) For one-time spot purchases of office supplies
B) For short-term contracts under 30 days
C) For longer-term contracts where costs are likely to increase or decrease
D) When the supplier refuses to provide a cost breakdown
E) When the buyer wants to assume all financial risk
Correct Answer: C) For longer-term contracts where costs are likely to increase or decrease
Rationale: Escalation clauses allow for price adjustments (up or down) based on changes in
specific costs, which provides a safety net for both parties during long-term agreements.
Question 6
To ensure fairness, an escalation clause in a contract should ideally be tied to:
A) The supplier’s internal accounting reports
B) The buyer’s quarterly profit margins
C) An independent, published third-party index
D) The current interest rate of the Federal Reserve
E) A verbal agreement between the two CEOs
Correct Answer: C) An independent, published third-party index
Rationale: Using a neutral, third-party index (like the Consumer Price Index or a specific
commodity index) prevents either party from manipulating the price and ensures the
adjustment reflects true market conditions.
Question 7
Which contract type is best used when parties cannot accurately predict costs and quantities at
the start and agree to adjust the price at a predetermined future time based on actual experience?
A) Firm fixed price
B) Fixed price with redetermination
C) Time and materials
D) Cost plus fixed fee
E) Spot contract
, 3
Correct Answer: B) Fixed price with redetermination
Rationale: Redetermination contracts use a "best guess" base price and require a formal
review at a later date to adjust the price to reflect the actual cost experience of the supplier.
Question 8
How does a "Fixed price with incentives" contract typically function?
A) The buyer provides a gift to the supplier for finishing on time
B) The supplier is reimbursed for all costs plus a 100% markup
C) Terms allow for cost-savings sharing between the buyer and supplier
D) The price is determined by a random lottery
E) The supplier is penalized for every day the project is late
Correct Answer: C) Terms allow for cost-savings sharing with supplier
Rationale: Incentive contracts motivate suppliers to be efficient by allowing them to keep a
portion of the savings if they complete the work for less than the target cost.
Question 9
Under what conditions are "Fixed price with incentives" contracts typically utilized?
A) Low unit cost and short lead times
B) High unit cost and relatively long lead times
C) Non-critical items like paper clips
D) When the supplier has a monopoly
E) Only during international global sourcing
Correct Answer: B) Typically utilized under conditions of high unit cost and relatively long
lead times
Rationale: High costs and long durations provide enough room and time for the supplier to
find efficiencies that justify the administrative complexity of an incentive-based agreement.
Question 10
A "Cost plus incentive fee" contract is most appropriate when:
A) The parties have no idea what the final cost will be
B) The parties are confident of the initial target cost
C) The buyer wants to pay as little as possible without regard for quality
D) The supplier is in financial distress
E) The contract is for a simple commodity purchase
Correct Answer: B) Appropriate when parties are confident of initial target cost
Rationale: This contract is similar to the fixed-price version but focuses on allowable costs.
Confidence in the target cost allows the incentive structure to be meaningful and fair.
Question 11
In a "Cost-sharing" contract, what is the most critical requirement for success?
A) The use of a "not to exceed" amount