EET Civil Construction PE Conceptual
Questions and Correct Answers Exam
2026
The fineness modulus of three sand samples (A, B, and C) are 2.3, 2.5, and 2.7,
respectively. Which of the following statements is correct:
A) B is finer than A
B) C is finer than B
C) A is finer than C
D) Both A and B
C. The larger fineness modulus means coarser aggregates
If concrete beams are not available to measure modulus of rupture, the tensile strength
of concrete is directly measured by _______ test.
split tensile
What is the main reason of using fly ash in concrete?
A) Reducing cement volume
B) Higher stiffness
C) Faster gain of compressive strength D) Lighter concrete
A. The main reason is reducing the volume of cement needed.
Which of the following statements is NOT correct about effect of fly ash on concrete
properties?
A) Increase of workability
B) Earlier gain strength
C) Reduction of air content
D) Reduction in water
B. Fly ash replaces cement therefore reduces the rate of strength gain or delays the
strength gain.
Ready-mixed 4000-psi concrete being delivered to a jobsite is found by the third-party
inspector to have a slump less than the 6 in. specified. Which of the following is the
most appropriate corrective action?
A) Decrease the amount of water in the mix before the truck leaves the ready-mix plant.
B) Increase the water to the mix in the truck at the jobsite before the concrete is poured.
C) Increase the rotation speed of the mixing drum while the truck is in transit to the
jobsite.
D) Add an admixture to the mix in the truck at the jobsite before the concrete is poured.
CIVIL
,CIVIL
D.
The w/cm ratio cannot be altered, while the number of drum revolutions can affect
slump and entrained air content.
Therefore, keeping a consistent number of revolutions (typically limited to 300-
revolutions) on a specific mixture and project helps the ready-mix producer consistently
compensate for any such changes.
More importantly, operating a drum at high speeds when driving is a serious safety risk
Increase of carbon content of steel will result in:
A) Increase in toughness
B) Decrease in modulus of elasticity
C) Increase in tensile strength
D) Increase in energy needed to break samples of the steel
c - Increase in carbon content increases tensile strength
Plywood consists of multiple plies with the grain of each layer running in ________
directions
opposite
After the placement of a reinforced concrete wall in a commercial building, the owner
suspects internal defects in the structural element due to the low slump of concrete and
wants to examine this possibility. No damage to the structure is allowed by the
engineer. Which test method can be used to identify the potential internal defects?
Select all that apply.
A) Impact-echo
B) Sounding
C) Infrared thermography
D) Impulse response
E) Probe penetration
A&D
According to the Nondestructive Test Methods for concrete table Section 2.5.3.2 of the
NCEES Civil Reference Handbook, internal defects can be identified by impact-echo,
ultrasonic and impulse response.
The project's specification for cast-in-place concrete requires a f'c of 3000-psi. Which of
the following individual test breaks (psi) indicate(s) a failure?
A) 2900
B) 3000
C) 3400
D) None of the above
D
It is important to understand that an individual test falling below ƒ´c does not necessarily
constitute a failure to meet specification requirements. When the average of strength
tests on a job are at the required average strength, f'cr, the probability that individual
CIVIL
,CIVIL
strength tests will be less than the specified strength is about 10% and this is accounted
for in the acceptance criteria.
When strength test results indicate that the concrete delivered fails to meet the
requirements of the specification, it is important to recognize that the failure may be in
the testing, not the concrete. This is especially true if the fabrication, handling, curing
and testing of the cylinders are not conducted in accordance with standard procedures.
Ready-mixed 4000-psi concrete being delivered to a jobsite is found by the third-party
inspector to have a slump less than the 6 in. specified. Which of the following is the
most appropriate corrective action?
A) Decrease the amount of water in the mix before the truck leaves the ready-mix plant
B) Increase the water to the mix in the truck at the jobsite before the concrete is poured
C) Increase the rotation speed of the mixing drum while the truck is in transit to the
jobsite
D) Add an admixture to the mix in the truck at the jobsite before the concrete is poured
D
The w/cm ratio cannot be altered, while the number of drum revolutions can affect
slump and entrained air content.
Therefore, keeping a consistent number of revolutions (typically limited to 300-
revolutions) on a specific mixture and project helps the ready-mix producer consistently
compensate for any such changes.
More importantly, operating a drum at high speeds when driving is a serious safety risk.
A State DOT initiates a project to construct a maintenance facility for the housing of
snow plows. The footprint of the building falls within state property however there is a
need to store materials in an area past the property line of an adjacent privately owned
facility. Which of the following is the most appropriate Right of Way action to take to
complete the project?
A) Temporary Easement
B) Permanent Easement
C) Property Acquisition
D) No action required
A
The work which takes place within the adjacent property is temporary in nature and the
current owner will maintain rights of the property and therefore a temporary easement
would be required.
Which of the following project management tools is used to evaluate a project's
performance and progress by integrating the project scope, schedule and cost?
A) Work breakdown structure (WBS)
B) Performance Evaluation and Review Technique (PERT)
CIVIL
, CIVIL
C) Six Sigma SIPOC Diagram
D) Earned Value Management (EVM)
D
Earned Value Management is a project management tool used to evaluate a project's
performance and progress by integrating the project scope, schedule and cost. The
EVM method is used to determine the true value of a project's performance by
comparing the planned value of the work to be done with the earned value of the work
actually completed and the actual costs spent to complete the work
A Class 1 cost estimate for the construction of a $130,000,000 office building may have
an accuracy range ($) of:
A) $7,800,000
B) $16,900,000
C) $19,500,000
D) $45,500,000
C
Use the information found in the PE Handbook Cost Estimate Classification Matrix for
Building and General Construction Industries table. Refer to the column labeled
"Expected Accuracy Range (typical variation in low and high ranges at an 80%
confidence interval)" to find the matching statement to the example. Class 1 expected
accuracy range is found in the as Low: -3% to 5% and High: +3% to +10%. Using the
maximum range of low 5% to high +10% finds a 15% spread between the accuracy,
which is 15% of $130,000,000 = 19,500,000.
What is the best way to minimize pollution and damage at a blasting site near structures
or highways?
A) Reduce the number of the holes in the ground
B) Blasting Mats
C) Keep the trees in place until the day before blasting
D) Insofar as possible, blasting operations above ground shall be conducted between
noon and sundown
B
When blasting is done in congested areas or in proximity to a structure, railway, or
highway, or any other installation that may be damaged, the blaster shall take special
precautions in the loading, delaying, initiation, and confinement of each blast with mats
or other methods so as to control the throw of fragments, and thus prevent bodily injury
to employees.
In a cantilever retaining wall, if the soil's internal friction angle is increased, the active
soil pressure exerted on the wall will ________.
decrease
The following equation can be used to verify this: K = (1 sinɸ)/(1+sinɸ) (HB Page #72)
CIVIL