ICC RF Residential Fire Sprinkler Inspector-Plans
Examiner Exam Actual Verified Test Questions and
Correct Answers With Rationales LATEST THIS
YEAR.pdf||Newest Exam!!!
When the fire code official observes a violation, a written
notice of violation shall be prepared. After the notice is
served and the responsible person has not complied
within the time specified, the next course of action would
be for _____. - Answer-the fire code official to request
legal counsel to institute appropriate legal procedures
Where approved by the fire code official, the ratio of
trained crowed managers required for facilities or events
where more than, 1,000 persons congregate may be
reduced where the facility is equipped with which of the
following? - Answer-Fire protection warranting a reduction
A maximum of ___ percent of the number and required
exit width of interior exit stairways and ramps may egress
through a vestibule provided all of the required provisions
are met. - Answer-50
,2|Page
Interconnection of smoke alarms is required in all of the
following occupancies except___. - Answer-E day care
Which of the following is not a recognized alternative fire-
extinguishing system? - Answer-Halon 1201 extinguishing
system
The permit threshold for carbon dioxide used in insulated
carbon dioxide beverages dispensing applications is ____
cu. ft. at NTP. - Answer-875
If the fire code official refuses to issue a permit, the fire
code official must take which of the following actions? -
Answer-Explain the reasons in writing
"An alkaline storage battery in which the positive active
material is nickel oxide, the negative contains cadmium
and the electrolyte is potassium hydroxide" best describes
which of the following battery types? - Answer-Nickel-
cadmium
According to the IFC, existing opening protectives for
floors and shafts are permitted to employ fusible links
where the link temperature does not exceed _____ degree
F. - Answer-135
,3|Page
Exterior walls of a Group S-1 aircraft hanger within 20 feet
of a public way or lot line must have a fire-resistance
rating of not less than ____ hours. - Answer-2
When an installation subject to inspection prior to use is
covered or concealed without having been inspected, fire
code official has the authority to ____. - Answer-Require
the work be exposed for inspection
In a new construction, nonstructural projections such as
trim and similar decorative features are permitted to
project into the required egress width not more than ____
inches on each side. - Answer-1-1/2
In new construction, stairways in a nonsprinklered building
that are part of the accessible means of egress for the
exterior area for assisted rescue shall be not less than ___
inches between handrails. - Answer-48
In new construction, doors opening onto a ramp landing in
the means of egress shall not reduce the clear width to
less than____ inches. - Answer-42
, 4|Page
A pile of wooden pallets containing more than 287 pallets
shall be located at least____ feet from a masonry wall that
has plan grass openings and open fire sprinklers. -
Answer-20
Refresher training on the proper use of portable fire
extinguishers for employees of a correctional center must
be provided at least____. - Answer-annually
For means of egress purposes, the restaurant occupant
load based on 20 booths with a combined booth seat
length of 180 feet is _____. - Answer-90
A building that manufactures dried hemp products is
classified as a Group____ occupancy. - Answer-F-1
Which of the following uses is not classified as a Group E
occupancy? - Answer-University classroom
A liquid, as defined in the International Fire Code, has a
boiling point temperature greater than ____ degrees F. -
Answer-68