When the angle of a cranes boom is between two angles listed on the chart, you must use
|| || || || || || || || || || || || || || || || || ||
which angle listed?
|| ||
a. Next higher angle listed
|| || || ||
b. Next longer angle listed
|| || || ||
c. Next lower angle listed
|| || || ||
d. Next shorter angle listed
|| || || ||
c. Next lower angle listed
|| || || ||
When operating a crane and you boom down. What does the radius do?
|| || || || || || || || || || || ||
a. Decrease
||
b. Increase
||
c. Don't change
|| ||
b. Increase
||
Most Digger Derricks will allow an operator to pick loads up to what degree out of level?
|| || || || || || || || || || || || || || || ||
a. Up to 3 degrees
|| || || ||
b. Up to 4 degrees
|| || || ||
c. Up to 5 degrees
|| || || ||
d. Up to 6 degrees
|| || || ||
c. Up to 5 degrees
|| || || ||
,2
When does an erected jib have its greatest effect on the crane?
|| || || || || || || || || || ||
a. Long boom, high boom angle
|| || || || ||
b. Short boom, high boom angle
|| || || || ||
c. Long boom, low boom angle
|| || || || ||
d. Short boom, low boom angle
|| || || || ||
c. Long boom, low boom angle
|| || || || ||
Most boom truck load charts are based on what percent of tipping?
|| || || || || || || || || || ||
a. 75%
||
b. 80%
||
c. 85%
||
d. 100%
||
c. 85%
||
While performing a shift inspection on a crane and there is water accumulation around the
|| || || || || || || || || || || || || || ||
outrigger, what must be done? || || || ||
a. Nothing
||
b. Drained
||
c. Filled in
|| ||
d. Add cribbing
|| ||
b. Drained
||
,2
When leveling a crane where would be the best location to place the level?
|| || || || || || || || || || || || ||
a. Outriggers
||
b. Upper works
|| ||
c. Carrier
||
d. Deck
||
b. Upper works
|| ||
Most crane manufacturers do not permit additional ? to be added to the crane?
|| || || || || || || || || || || || ||
a. Fire extinguisher
|| ||
b. Toolboxes
||
c. Labels/decals
||
d. Mirrors
||
b. Toolboxes
||
If a crane has a stod jib on while lifting a load , the jib deduction is based on the ?
|| || || || || || || || || || || || || || || || || || || ||
a. Effective weight
|| ||
b. Actual weight
|| ||
c. Assumed weight
|| ||
d. Not deducted
|| ||
a. Effective weight
|| ||
What may occur when operating a crane that is out of level and you swing to low side?
|| || || || || || || || || || || || || || || || ||
, 2
a. Radius decease
|| ||
b. Radius increase
|| ||
c. Boom length increases
|| || ||
d. Boom angle increases
|| || ||
b. Radius increase
|| ||
While operating a boom truck near a reinforced retaining wall , it is recommended to stay
|| || || || || || || || || || || || || || || ||
back?
a. 2 to 1
|| || ||
b. 1 to 1
|| || ||
c. 3 to 1
|| || ||
d. 1/2 to 1
|| || ||
b. 1 to 1
|| || ||
When a proper working A2B is activated what operations stop?
|| || || || || || || || ||
a. swing, boom up
|| || ||
b. Hoist up, boom down
|| || || ||
c. Swing
||
d. Hoist down, boom up
|| || || ||
b. Hoist up, boom down
|| || || ||
According to OSHA 1926 subpart cc monthly inspection records must be retained for a
|| || || || || || || || || || || || || ||
minimum of ? || ||
a. 30 days
|| ||