• Boiler Operation and High-Pressure Steam Systems
• HVAC Maintenance and Repair
• NYC Building Codes and Safety Regulations
• Personnel Management and Budgeting
• Electrical Systems and Motor Maintenance
• Fire Suppression and Alarm Systems
• Environmental Health and Safety
INTRODUCTION
The NYC Custodian Engineer Exam is designed to evaluate the competency of
individuals responsible for the
operation, maintenance, and administration of large-scale public facilities. This
assessment measures a
candidate’s technical knowledge of mechanical systems, including high-pressure
boilers and HVAC units, alongside
essential administrative skills such as labor relations and safety compliance.
,Through multiple-choice
questions and scenario-based problems, the exam emphasizes real-world
application and critical decision-making.
Candidates must demonstrate a thorough understanding of NYC building codes and
safety protocols to ensure the
efficient and safe management of school buildings and public infrastructure under
demanding conditions.
SECTION ONE: QUESTIONS 1–100
1. What is the primary purpose of a "bottom blowdown" on a steam boiler?
A. To increase the water level rapidly
B. To remove sludge and sediment from the mud drum
C. To decrease the concentration of dissolved oxygen
D. To clean the internal surfaces of the fire tubes
🟢 B. Option
🔴 Explanation: Bottom blowdown is performed to remove accumulated solids, sludge,
and sediment that settle at the lowest point of the boiler, preventing scale buildup and
potential tube failure.
, 2. A Custodian Engineer notices a significant drop in the building’s vacuum heating
system pressure. Which component should be checked first?
A. The condensate return pump
B. The main steam header valve
C. The thermostatic radiator traps
D. The expansion tank sight glass
🟢 C. Option
🔴 Explanation: Failed thermostatic traps are the most common cause of vacuum loss in
a steam heating system, as they allow live steam to enter the return lines.
3. Under NYC building codes, how often must a high-pressure boiler be inspected by a
qualified inspector?
A. Once every two years
B. Annually
C. Semi-annually
D. Every five years
🟢 B. Option
, 🔴 Explanation: NYC regulations require high-pressure boilers to undergo an annual
internal and external inspection to ensure safety and operational integrity.
4. Which of the following is the correct procedure for testing a low-water fuel cut-off
(LWCO)?
A. Close the main steam stop valve
B. Increase the burner firing rate
C. Slowly drain the water column while the burner is firing
D. Shut off the feedwater pump and wait for evaporation
🟢 C. Option
🔴 Explanation: Draining the water column while the burner is on is the standard test to
ensure the LWCO will effectively shut down the fuel supply if water levels drop below the
safe limit.
5. What is the main advantage of using a centrifugal pump over a reciprocating pump
for feedwater?
A. Higher pressure capability
B. Ability to handle large volumes at constant pressure