CON 3990 Newest Exam with accurate detailed answers
|| || || || || || ||
What is the Micro-purhcase threshold for supplies? - ✔✔$10k
|| || || || || || || ||
All incentive contracts (schedule or performance) must also include what? - ✔✔Cost
|| || || || || || || || || || || ||
incentive or constraint || ||
What requires funds to be used only for needs or services in the year of the appropriations
|| || || || || || || || || || || || || || || || ||
obligation period? - ✔✔Bona Fide Needs Rule || || || || || ||
What contract types can be used for commercial item purchases? - ✔✔FFP or FPEPA
|| || || || || || || || || || || || ||
What is the Simplified Acquisition Threshold for commercial products and services? What is
|| || || || || || || || || || || || ||
it for non-commercial? - ✔✔$7.5M - commercial $250k for non-commercial
|| || || || || || || || ||
True or False: The Gov shall use electronic commerce whenever practicable or cost-effective
|| || || || || || || || || || || || ||
- ✔✔True
||
What is the purpose of a contract file? (4) - ✔✔Provide background/basis for decisions
|| || || || || || || || || || || || ||
Supporting actions taken || ||
Provide information for reviews and investigations
|| || || || ||
Furnishing essential facts in the event of a litigation
|| || || || || || || ||
Can contract files be combined if appropriate? - ✔✔Yes
|| || || || || || || ||
At what level are contract files maintained and why? - ✔✔Maintained at the organizational
|| || || || || || || || || || || || || ||
level to ensure || ||
,2
effective documentation of contract actions
|| || || ||
accessibility by principal users || || ||
minimal establishment of duplicate and working files
|| || || || || ||
safeguarding classified docs || ||
conformance with agency regs || || ||
When is a SAP contract file closed out? - ✔✔When the KO receives evidence of receipt of
|| || || || || || || || || || || || || || || || ||
property or final payment || || ||
When is a FFP (not SAP) contract file closed out? - ✔✔Should be closed out within 6
|| || || || || || || || || || || || || || || || ||
months after date KO receives evidence of physical completion
|| || || || || || || ||
When should contract files required settlement of indirect cost rates be closed out? -
|| || || || || || || || || || || || || ||
✔✔Within 36 months of the month the KO receives evidence of physical completion
|| || || || || || || || || || || ||
When should all other (not SAP, FFP, or indirect cost rate) contract files be closed? -
|| || || || || || || || || || || || || || || ||
✔✔Within 20 months of the month the KO receives evidence of physical completion
|| || || || || || || || || || || ||
When is a contract considered physically complete? - ✔✔the KTR has completed required
|| || || || || || || || || || || || ||
deliveries and Gov has inspected and accepted the supplies
|| || || || || || || ||
The contractor has performed all services and the Gov has accepted the services and
|| || || || || || || || || || || || || ||
all option provisions, if any, have expired
|| || || || || ||
or the Gov gives the KTR notice of termination
|| || || || || || || ||
What are the steps to close out a contract file? - ✔✔1) Contract admin office is responsible
|| || || || || || || || || || || || || || || ||
for initiating, reviewing contract fund status, and deobligating excess funds
|| || || || || || || || || ||
2)KO issues a contract completions statement
|| || || || ||
3) KO files completed statement and signed copy send to admin office
|| || || || || || || || || || ||
, 2
How long are contract documents retained after closeout? - ✔✔6 years after final payment
|| || || || || || || || || || || || ||
What does a KO need prior to commencement of negotiations for a sole source contract,
|| || || || || || || || || || || || || || ||
commencement of negotiations for a contract resulting from an unsolicited proposal, or
|| || || || || || || || || || || ||
award without providing for full and open competition? - ✔✔Justification and Approval
|| || || || || || || || || || || ||
which justifies the actions in writing, certifies the accuracy and completeness of the
|| || || || || || || || || || || || ||
justifications and obtains the approval required || || || || ||
The KO shall not award a sole-source contract for an amount exceeding $25M unless -
|| || || || || || || || || || || || || || ||
✔✔they have a signed Justification and Approval
|| || || || || ||
A J&A should include - ✔✔Description of action being approved
|| || || || || || || || ||
Description of supplies or services required + estimated value
|| || || || || || || ||
statutory authority permitting other than full and open comp
|| || || || || || || ||
demonstrate why specific KTR is required (instead of comp) || || || || || || || ||
efforts made to solicit offers from other sources
|| || || || || || ||
determination of fair and reasonable anticipated cost || || || || || ||
description of market research conducted || || || ||
list of sources that expressed interest
|| || || || ||
statement of how agency may remove comp barriers in the future
|| || || || || || || || || ||
KO certification
||
What are the thresholds for J&A approval - ✔✔under $750 - KO approval
|| || || || || || || || || || || ||
over $750k and under $100M - HCA
|| || || || || ||
over $100M - senior procurement executive
|| || || || ||