A CM's liability is determined solely by whether or not the CM
performed according to the required standard of care.
True False - ✔✔✔ Correct Answer > False
The CMAA Document A-3, General Conditions of the Construction
Contract between Owner and Contractor is intended to be used
where the owner has elected to use what type of CM contract?
A) CM-at-Risk
B) Agency CM
C) Design-build
D) Lump sum - ✔✔✔ Correct Answer > B) Agency CM
The possible approaches for delivering a project are virtually
unlimited. A key reason for such variations is:
A) The different roles that can be assumed by project
participants.
,Page 2 of 51
B) Different forms of contracts and methods of compensation
that can be used.
C) The different levels of care, responsibility, and risks assumed
by the parties involved.
D) All of the above. - ✔✔✔ Correct Answer > D) All of the above
In cases where a project is extended in duration for reasons
beyond the control of the CM, it is imperative that the CM
agreement address:
A) How changes in scope and additional services will be handled.
B) Extended CM services.
C) The cost of additional services.
D) All of the above - ✔✔✔ Correct Answer > D) All of the above
A QBS selection process will generally be based on what primary
criteria?
A) Price
B) Past experience
C) Qualifications
D) Fee - ✔✔✔ Correct Answer > C) Qualifications
,Page 3 of 51
The cost reimbursement method of compensation is one of the
most commonly used forms of CM compensation associated with
agency CM.
True False - ✔✔✔ Correct Answer > True
Under a GMP contract, with services provided by a CM-at-Risk,
which of the following statements is NOT true?
A) The GMP is usually established on less than 100% complete
drawings and specifications.
B) It is important that the phrase Guaranteed Maximum Price be
clearly defined in the contract regarding what it includes and
excludes.
C) With a GMP type CM agreement, the CM is responsible for all
costs associated with the project.
D) Once a GMP for construction costs is established, the CM
takes on the risk for completing the project. - ✔✔✔ Correct Answer >
C) With a GMP type CM agreement, the CM is responsible for all
costs associated with the project.
The traditional delivery system is characterized by executing the
major phases of a project in:
A) An overlapping concept
B) A linear sequence
C) A fast track method
, Page 4 of 51
D) All of the above - ✔✔✔ Correct Answer > B) A linear sequence
A key advantage of the traditional delivery approach is:
A) With the traditional delivery system, the cost of the
construction phase is known before construction starts.
B) Facility features are fully determined & specified.
C) When the construction contract is signed, the major risk
belongs to the contractor.
D) All of the above - ✔✔✔ Correct Answer > B) Facility features are
fully determined & specified.
Design-build and at-risk construction management delivery
systems allow the option to fast-track or phase a project.
True False - ✔✔✔ Correct Answer > True
Most definitions of construction management are similar.
However, a contractual definition is not known until:
A) The legal form of the CM contract is chosen.
B) The specific scope of services to be provided is identified.
C) The relationship of the CM to others and the risks and
authority assumed by the parties are clearly defined.
D) All of the above - ✔✔✔ Correct Answer > D) All of the above