FDOT Final Estimates - Level 1 Exam
Questions & Answers (Grade A+)
What two types of Estimates are needed to pay for the work
performed by contractors? -
correct answer ✅Final & Progress Monthly
In case of discrepancies among the contract documents, which
document takes the highest precedence? -
correct answer ✅Special Provisions
Contractors Recieve progress payments on the basis of? -
correct answer ✅Monthly Progress Estimates
Which of the following sets forth the Department's methods and
procedures for preparing and checking final estimates? -
correct answer ✅Preparation and Documentation Manual (PDM)
Which Document contains a series of Specially designed forms that
show both original estimates of quantities and the final quantities
as measured ad accepted? -
correct answer ✅Computation Books
, FDOT Final Estimates - Level 1 Exam
Questions & Answers (Grade A+)
Which Document contains alignment notes, cross-section notes,
linear and area measurements and dimension sketches? -
correct answer ✅Field Notebooks
Where are major changes during construction documented and
"as-built" conditions shown? -
correct answer ✅Field Notebooks
What identification is needed to show on the front cover of a field
book? -
correct answer ✅FEID, Contract number, General contents of the
book
When making corrections to a field book entry, you should: -
correct answer ✅strike through, initial and enter correct data and
date
What should be started on the first lined page (page 1) of a field
book? -
correct answer ✅INDEX
Questions & Answers (Grade A+)
What two types of Estimates are needed to pay for the work
performed by contractors? -
correct answer ✅Final & Progress Monthly
In case of discrepancies among the contract documents, which
document takes the highest precedence? -
correct answer ✅Special Provisions
Contractors Recieve progress payments on the basis of? -
correct answer ✅Monthly Progress Estimates
Which of the following sets forth the Department's methods and
procedures for preparing and checking final estimates? -
correct answer ✅Preparation and Documentation Manual (PDM)
Which Document contains a series of Specially designed forms that
show both original estimates of quantities and the final quantities
as measured ad accepted? -
correct answer ✅Computation Books
, FDOT Final Estimates - Level 1 Exam
Questions & Answers (Grade A+)
Which Document contains alignment notes, cross-section notes,
linear and area measurements and dimension sketches? -
correct answer ✅Field Notebooks
Where are major changes during construction documented and
"as-built" conditions shown? -
correct answer ✅Field Notebooks
What identification is needed to show on the front cover of a field
book? -
correct answer ✅FEID, Contract number, General contents of the
book
When making corrections to a field book entry, you should: -
correct answer ✅strike through, initial and enter correct data and
date
What should be started on the first lined page (page 1) of a field
book? -
correct answer ✅INDEX