The Quality Control Plan contains: - ANSWER✔️Identification of individual quality quality
control personnel, including name, qualifications, assigned duties, responsibilities and
authorities.
The preconstruction conference and the coordination and mutual understanding meeting (Navy)
are: - ANSWER✔️Conducted prior to the commencement of any physical construction work.
A cumulative list of job deficiencies/rework items can be found in: - ANSWER✔️A deficiency
tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and meeting (Navy)? -
ANSWER✔️To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of Control. -
ANSWER✔️Safety.
,Submittals are: - ANSWER✔️Necessary to demonstrate that the proposed materials, etc. are in
compliance with the contract.
All submittals for government approval must be provided by the _________________ in time to
allow for the review, approval, procurement, delivery, and performance of preparatory phase for
an item before it is needed for construction. - ANSWER✔️Contractor to the Government
The means for enforcing contract compliance are provided in the: - ANSWER✔️Contract clauses
of the contract.
ENG Form 4288-R, the submittal register: - ANSWER✔️Identifies those submittals requiring
government approval
The primary purpose of the Three-Phase control system is to: - ANSWER✔️Require the
contractor to plan and schedule his work.
The contractor is required to conduct a preparatory phase meeting before he begins any definable
feature of work except when: - ANSWER✔️There are no exceptions to the rule.
The ____________________ is the appropriate time to assure that all materials and/or equipment
have been tested, submitted, and approved. - ANSWER✔️Preparatory phase
The ____________________ is workmanship oriented, and where workmanship standards are
established. - ANSWER✔️Initial phase
The contract requires the contractor to submit quality control reports: - ANSWER✔️Daily.
The Quality Control report should address: - ANSWER✔️Both work completed and control
activities
The Quality Assurance Report is the governments record of project-related events and is
prepared _______________. - ANSWER✔️For each visit day
Grounds for withholding payment include the contractors failure to: - ANSWER✔️Perform in
accordance with the terms of the contract, provide a Quality Control Plan giving assurance of
intent and ability to comply with quality standards, and build to the quality standards established
by the contract.
Actual construction on the job site begins: - ANSWER✔️After an interim or final QC Plan is
accepted.
The purpose of Construction Quality Management is to: - ANSWER✔️Achieve the quality
established by properly developed requirements through the combined responsibility, but
seperate efforts of contractpr smd government personnel.
, Construction Quality Management is the performance of tasks, which ensure that construction is
performed. - ANSWER✔️According to plans and specifications, on time, within a defined budget
and a safe work environment.
Partnering relationships are based upon: - ANSWER✔️Building trust and dedication to common
goals
It is the responsibility of Quality Assurance Personnel to: - ANSWER✔️Periodically verify that
the contractors system of control is working effectively.
An effective contractor quality control program will: - ANSWER✔️Be an incentive for work to
be done correctly the first time resulting in earlier completion, reduced field overhead costs, and
greater profits.
The success or failure of all contractors is based upon: - ANSWER✔️The ability to control costs,
finance work, estimate jobs, schedule the work, and maintain effective quality control.
Quality Assurance Personnel have the responsibility to: - ANSWER✔️Require contractors to
maintain the quality specified in the plans and specifications.
Inspection is: - ANSWER✔️The process by which ongoing and completed work is examined
Design-Build contracts require: - ANSWER✔️The QC Manager to be in place and take an active
role in the review and coordination of the design.
The purpose of Construction Quality Management is to: - ANSWER✔️Achieve the quality
established by properly developed requirements through the combined responsibility, but
seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that construction is
performed. - ANSWER✔️According to plans and specifications, on time, within a defined budget
and a safe work environment.
Partnering relationships are based upon: - ANSWER✔️Building trust and dedication to common
goals
It is the responsibility of Quality Assurance Personnel to: - ANSWER✔️Periodically verify that
the contractors system of control is working effectively.
An effective contractor quality control program will: - ANSWER✔️Be an incentive for work to
be done correctly the first time resulting in earlier completion, reduced field overhead costs, and
greater profits.