TESTED QUESTIONS AND SOLUTIONS FULL
REVIEW GRADED A+
◉ Which of the following acronyms represents the level of charge
present in an EV battery?
• ANSI
• EVA
• NFPA
• SOC Answer: • SOC
◉ Wireless EV charging utilizes the principles of which of the
following?
• Inductance
• Parallel resonant circuits
• Series resonant circuits
• All of the above Answer: • Inductance
◉ • It is important to conduct a site visit for EVSE installation for
which of the following reasons?
, • It allows the installer to learn what the perspective costumer
needs out of an EVSE installation.
• It lets the installer tell the perspective costumer what they have to
do.
• It provides an opportunity to gather facts and present oneself as a
knowledgeable professional.
• Both a. and c. Answer: • Both a. and c.
◉ Additional EVSEs are to be added to an existing 120/208 - volt,
3-phase, 4-wire, 600-amperes service with 220 amperes of non-
continuous load and 172 amperes of continuous load. The EvSes
each draw 32 amperes. How many new EVSEs may be added to the
service?
•5
•6
•7
• 8 Answer: • 6
◉ Which part of Article 110 covers requirements for working space
around electrical equipment
• ll
•lll
•v