Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

NERC PRACTICE EXAM NEWEST ACTUAL EXAM COMPLETE 240 QUESTIONS WITH DETAILED VERIFIED ANSWERS (100% CORRECT ANSWERS) / NERC CERTIFICATION PRACTICE UPDATED VERSION ACTUAL EXAM /ALREADY GRADED A+

Beoordeling
-
Verkocht
-
Pagina's
36
Cijfer
A+
Geüpload op
01-05-2026
Geschreven in
2025/2026

NERC PRACTICE EXAM NEWEST ACTUAL EXAM COMPLETE 240 QUESTIONS WITH DETAILED VERIFIED ANSWERS (100% CORRECT ANSWERS) / NERC CERTIFICATION PRACTICE UPDATED VERSION ACTUAL EXAM /ALREADY GRADED A+

Instelling
NERC
Vak
NERC

Voorbeeld van de inhoud

NERC PRACTICE EXAM NEWEST ACTUAL EXAM
COMPLETE 240 QUESTIONS WITH DETAILED VERIFIED
ANSWERS (100% CORRECT ANSWERS) / NERC
CERTIFICATION PRACTICE UPDATED VERSION ACTUAL
EXAM /ALREADY GRADED A+



A simple power system is composed of three lines connecting generation to load.
Each lines the same impedance, is initially loaded at 200 MW, and has a thermal
limit of 400 MW. If one line trips, what the loading on the shortest remaining line
be and will the thermal limit either remaining line be violated? - CORRECT
ANSWER ✔✔- 300 MW and No


The best prediction of system load is the load forecast tool that uses? - CORRECT
ANSWER ✔✔- Forecasted Weather


If the phase angel at an open breaker is equal to 1/10 of a cycle, this is the the
same angle as? - CORRECT ANSWER ✔✔- 1/10 of 360 so 36


A ___________ tool is used to ensure the power system can respond within
acceptable limits of N-1 - CORRECT ANSWER ✔✔- Contingency Analysis


Which of the following activities would not be included in the procedures for
transmission reliability? - CORRECT ANSWER ✔✔- Ancillary service pricing




1|Page

,The transmission Operator and BA shall provide documentation that operating
personnel have ______ to implement real time actions to ensure the stable and
reliable operation of the BES. - CORRECT ANSWER ✔✔- Proper NERC Certification
Credential


A utility distribution bus has the following customer loads attached. What is the
total customer MW load and is the total customer load capacitive or inductive? 5
MW 1 MVAR & 3 MW 1 MVAR & 2 MW -2 MVAR & 10 MW 3 MVAR - CORRECT
ANSWER ✔✔- 20 mw and Inductive


How many MVARs does a 230 kV, 50 MVAR capacitor bank provide when the
voltage id 207 kV - CORRECT ANSWER ✔✔- Actual MW/ Rated MW ^2 x Capacitor
Rating
40


You are a system operator and the load forecast is for an all time summer peak
load day, generations and reactive resources will be tight. Which scheduled job
would you allow to proceed? - CORRECT ANSWER ✔✔- 735 kV shunt reactor
maintenance.


A contingency results in the exceedance of an IROL. What could be the result if
the IROL is allowed to be exceeded longer than T sub v - CORRECT ANSWER ✔✔-
Interruption of power to a large part of the BES


Generators have the ability to be used as voltage control devices. If a generator
raises its VAR output, the system orator should expect system stage to? -
CORRECT ANSWER ✔✔- Increase




2|Page

,The actual voltage is 362kV on a 345 bus. What is the p.u. voltage? - CORRECT
ANSWER ✔✔- 1.05


In the initial stages of a system restoration condition high transmission system
voltage problems are more likely than low transmission system voltage problems
why? - CORRECT ANSWER ✔✔- Because of excessive MVAR supply from the
energization of transmission lines


All transmission operators shall operate so that instability uncontrolled separation
or cascading outages will not occur in result of? - CORRECT ANSWER ✔✔- Most
severe single contingency MSSC


A 230kV transmission line is energized at 230kV and is 100 miles long. What is the
approximate line charging contribution? - CORRECT ANSWER ✔✔- 30MVAR


When the system is on the verge of a voltage collapse and nothing else can be
done to alleviate the problem, operating personnel should? - CORRECT ANSWER
✔✔- Shed Load


The transmission operator shall take corrective actions necessary to prevent
voltage collapse when reactive resources are insufficient including? - CORRECT
ANSWER ✔✔- Shedding Load


There is a SPS/RAS system out of service for maintenance in your BA. What
actions do you take? - CORRECT ANSWER ✔✔- Operate within system limits that
the SPS/RAS is designed to protect against




3|Page

, If a BA has 500 MW of spinning Reserves and of that 300 MW are Regulating
Reserves by definition NERC requires the Regulating Reserves must be? -
CORRECT ANSWER ✔✔- On line and AGC responsive


What is the approximate MVAR/Mile production for a 345kV line? - CORRECT
ANSWER ✔✔- 3/4


The MSSC for your BA Area is 850 MW. A defined disturbance for DCS reporting
would be qual to how many MWs? - CORRECT ANSWER ✔✔- 680


Of the following which would be the best indicator of voltage collapse prone
conditions? - CORRECT ANSWER ✔✔- Low reactive power reserves


If the phase angle add an open breaker is equal to 1/10 of a cycle this is the same
as an angle of _____________degrees - CORRECT ANSWER ✔✔- 36


A__________Tool is used to ensure the power system can respond within
acceptable limits N-1conditions? - CORRECT ANSWER ✔✔- Contingency analysis


A transmission line is operating with a voltage phase angle different of 30 degrees
between the sending Vs and the receiving bus Vr. If the receiving end load is
suddenly increased, the voltage phase angle difference will be? - CORRECT
ANSWER ✔✔- The phase angle will increase. When load is increased phase angle
will increase.


A load has a power factor of 0.9 lagging. If the load draws 100 MVA, what is the
MW draw? - CORRECT ANSWER ✔✔- 90 pf= mw/mva


4|Page

Geschreven voor

Instelling
NERC
Vak
NERC

Documentinformatie

Geüpload op
1 mei 2026
Aantal pagina's
36
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$19.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
PrepMaster NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
216
Lid sinds
1 jaar
Aantal volgers
16
Documenten
2216
Laatst verkocht
17 uur geleden
ExamZen

A GOLD-TOP RATED SELLER ON STUVIA WITH WELL DETAILED AND VERIFIED STUDY DOCUMENTS ASSURED WITH EXCELLENT AND REMARKABLE RESULTS. Welcome to ExamZen, your go-to source for high-quality test banks and study materials designed to help you excel academically. We offer a comprehensive range of resources including test banks, study guides, solution manuals, and other study materials, all meticulously curated to ensure accuracy and effectiveness. Our affordable, instantly accessible materials are complemented by excellent customer support, making your learning experience seamless and efficient. Trust ExamZen to be your partner in academic success, providing the tools you need to achieve your educational goals.

Lees meer Lees minder
4.8

306 beoordelingen

5
265
4
29
3
3
2
2
1
7

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen