The CMAA Document A-3, General Conditions of the
Construction Contract between Owner and Contractor is
intended to be used where the owner has elected to use what
type of CM contract?
A) CM-at-Risk
B) Agency CM
C) Design-build
D) Lump sum - correct answer-B) Agency CM
Arbitration hearings are governed by the same rules of
evidence as a court proceeding.
True False - correct answer-False
All forms of alternative dispute resolution are voluntary
procedures.
True False - correct answer-True
, Page | 2
Arrangements to select a form of alternative dispute resolution
can be made by contractual agreement or at the time a dispute
arises.
True False - correct answer-True
A mediator cannot impose an agreement upon the parties.
True False - correct answer-True
The mediation record, including settlement offers, can be used
in later judicial proceedings.
True False - correct answer-False
A mini-trial, whether required by contract or agreed to
voluntarily, results in a binding decision.
True False - correct answer-False
The provisions and structure of a Dispute Review Board are
incorporated in a contract document.
True False - correct answer-True
, Page | 3
A Dispute Review Board does not meet until there is a dispute.
True False - correct answer-False
Usually Dispute Review Board recommendations are not
binding upon the parties, but recommendations of the DRB are
generally accepted.
True False - correct answer-True
The subcontractors and their foremen are not necessary
participants in a partnering workshop.
True False - correct answer-False
The parties, namely, the owner, the designer, CM, contractor
and others, can be described as stakeholders.
True False - correct answer-True
Partnering is a commitment among contracting parties that
changes the terms of a contract agreement.
True False - correct answer-False
, Page | 4
Experience shows that there is no increased staff or
management time required to initiate the partnering process.
True False - correct answer-True
The partnering process must be mandated by contract
provisions.
True False - correct answer-False
The partnering workshop structure, including length of the
workshop, is flexible depending upon project needs, project
size and budgetary considerations.
True False - correct answer-True
Prior to the workshop it is helpful to have job site interviews
with field representatives of the parties.
True False - correct answer-True
An outside facilitator is required to conduct the partnering
workshop.
True False - correct answer-True