Answers |Latest Version |Already Graded A+
Who participates in the Sprint Review? Select all applicable variants. ✔Correct Answer-* The
Key Stakeholders
* The Development Team
* The Product Owner
* The Scrum Master
The Sprint Backlog is created at the Sprint Planning. It is prohibited to add new work into the
Sprint Backlog later by the Development Team. ✔Correct Answer-False
The Development Team should be able to explain to the Product Owner and Scrum Master how
it intends to work as a self-organizing team to accomplish the Sprint Goal and create the
anticipated Increment. ✔Correct Answer-True
Scrum does not describe agile processes and techniques. ✔Correct Answer-True
What happens during the Sprint? Select three answers. ✔Correct Answer-*No changes are
made that would endanger the Sprint Goal
*Quality goals do not decrease
*Scope may be clarified and re-negotiated between the Product Owner and Development Team
as more is learned
Who is allowed to participate in the Daily Scrum? ✔Correct Answer-The Development Team
What is the Increment? ✔Correct Answer-The sum of all the Product Backlog items
completed during the Sprint and the value of the increments of all previous Sprints
Who is responsible for the monitoring of the remaining work towards the Project Goal?
✔Correct Answer-The Product Owner
Definition of "Done" is created during the first Sprint and remains unchanged until the Product
release. ✔Correct Answer-False
What is the result of the Sprint Review? ✔Correct Answer-A revised Product Backlog that
defines the probable Product Backlog items for the next Sprint
How does Definition of "Done" help to the Scrum Team? Select the three most applicable items.
✔Correct Answer-* DoD is used to assess when work is complete on the product Increment
* DoD ensures artifact transparency
, * DoD guides the Development Team in knowing how many Product Backlog items it can select
during a Sprint Planning
What are the two essential features a Scrum Team should possess? ✔Correct Answer-* It
should have all competencies needed to accomplish the work without depending on others not
part of the team
* It should choose how best to accomplish their work, rather than being directed by others
outside the team
Please, check all opportunities to inspect and adapt. ✔Correct Answer-The Daily Scrum
The Sprint Retrospective
The Sprint Planning
The Sprint Review
It is normal to have a "hardening" Sprint to remove all technical debt and prepare the Product
for upcoming release. ✔Correct Answer-False
Who participates in the Sprint Planning? Select three. ✔Correct Answer-The Product Owner
The Development Team
The Scrum Master
Other people than the Scrum Team can attend the Sprint Planning in order to provide technical
or domain advice. ✔Correct Answer-True
How much time does the Sprint Planning take? ✔Correct Answer-Not more than 8 hours
What comprises Scrum (select four)? ✔Correct Answer-Artifacts
Rules
Roles
Events
What are the formal Scrum events for inspection and adaptation? ✔Correct Answer-The
Sprint Planning
The Daily Scrum
The Sprint Retrospective
The Sprint Review
What happens when a Sprint is cancelled? Select three. ✔Correct Answer-If part of the work
is potentially releasable, the Product Owner typically accepts it
Any completed and "Done" Product Backlog items are reviewed
All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog