Answers |Latest Version |Guaranteed to Pass
These two things are considered Agile practices? ✔Correct Answer-1. Timeboxing
2. Test-Driven Development
The Scrum Master facilitates these three events in SAFe? ✔Correct Answer-1. Retrospective
2. Daily stand-up
3. Iteration Planning
Who participates in the backlog refinement event? ✔Correct Answer-The Agile Team
members & other Subject Matter Experts
3 pillars of Scrum ✔Correct Answer-Adaption, Transparency, Inspection
Empiricism ✔Correct Answer-Deriving knowledge through experience
12 Principles of Agile ✔Correct Answer-1. Satisfy customer (earlier the better)
2. Welcome changing requirements
3. Deliver working products frequently (2 week sprints)
4. Product Owner & developers should work together throughout the project
5. Build around motivated individuals
6. Face-to-face is most effective conversation
7. Working product is the Primary measure of progress
8. Agile process should promote sustainable development.
9. Technical excellence enhances agile
10. Simplicity - the art of maximizing the amount of work not done - is essential
11. Best products come from self-organizing teams
12. Reflect at regular intervals (retros)
Responsible for removing impedements ✔Correct Answer-Scrum master
Product Backlog ✔Correct Answer-Requirements for a system, expressed as a prioritized list
of product backlog Items:
functional and non-functional customer requirements
During a Sprint planning meeting, backlog items are moved from the product backlog into a
sprint, based on the product owner's priorities.
CCFOR ✔Correct Answer-courage, commitment, focus, openness, respect
Scrum Teams ✔Correct Answer-Self-organizing & Cross Functional
, Scrum Team Model ✔Correct Answer-Designed to optimize flexibility, creativity, &
productivity
Scrum Roles ✔Correct Answer-Product Owner
Scrum Master
Development Team
Product Owner role ✔Correct Answer-Maximizes the value of the product
Development Team role ✔Correct Answer-deliver a potentially releasable increment of
"Done" product at the end of each sprint
Scrum Master role ✔Correct Answer-promotes and supports Scrum theory, practices, rules,
and values
Scrum Artifacts ✔Correct Answer-Product Backlog
Sprint Backlog
Increment
Scrum Events ✔Correct Answer-Sprint Planning
Sprint
Daily Scrum
Sprint Review
Sprint Retrospective
Facilitation ✔Correct Answer-Fluid process using a variety of tools, techniques, and activities
to:
empower participants
create clarity
invite collaboration
increase commitment
maximize productivity
Release Burndown Chart ✔Correct Answer-A release's progress. It shows how much work was
left to do at the beginning of each sprint comprising a single release. The scope of this chart is a
single release; however, a product burndown chart spans all releases.
Sprint Backlog ✔Correct Answer-Defines the work for a sprint, represented by the set of tasks
that must be completed to realize the sprint's goals, and selected set of product backlog items.
Sprint Retrospective ✔Correct Answer-Time-boxed event of 3 hours, or less, held at the end
of every sprint after the sprint review meeting. The team and ScrumMaster meet to discuss
what went well and what to improve in the next sprint.