● How many days does a contractor have to respond in writing to the
copy of claim that was sent by the commission? Answer: 10 days
● If within ________ after the commission gives notice , a contractor on
whose amount a claim was paid does not reimburse the fund in full, the
commission may sue the contractor for reimbursement. Answer: 60 days
● In addtion to full reimbursement of the fund, a contractor is
responsible to pay at least _________interest on the amount to
reimburse. Answer: 10 %
● The state can record a lien against any real property owners by the
contractor for a debt owed to the fund Answer: True
● If the commission pays a claim from the fund base on the actions or
omissions of a contractor, the commission may suspend the contractors
license until full reimbursement of the fund plus at least 10%interest